Pile concreting |
In progress |
Done 14 nos(P10a,P12a complete this week) |
Site level survey |
completed |
|
7 day Cube test |
Completed |
|
BSNL, KWA site inspection for utility shifting |
In progress |
|
KSEB site inspection for utility shifting |
completed |
|
KSEB utilities estimate |
In progress |
almost complete |
site clearing in thamarassery area |
In progress |
|
filling work towards thamarassery side |
In progress |
60m complete |
filling work in piling location |
Completed |
upto AP2 area |