Prevoius Weekly Reports
|
weekly progress 30.9.2011 |
| |
|
shifting of utilities |
In progress |
|
|
KWA (PHED) sewage line |
completed |
|
|
KWA Water supply line |
completed |
|
|
|
|
|
|
KSEB |
In progress |
complete on Petta side,90% completed on anayara side |
|
transformer shifting on anayara side |
In progress |
|
|
BSNL |
completed |
|
|
| |
| Back |
| |
TRIAL PIT
|
| | |
TRANSFORMER FOUNATION
|
| | |
TRANSFORMER
|
| | |
|
| |
|