Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 7888652
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   Weekly progress report as on 30.09.2011
    

 

SlNo

Activity –which can be completed without caution

Description

Total Quantity

Cumulative progress up to this week

(1)

Balance  work

(2)

Cumulative delay in weeks after

Spplagmnt

(3)

Work  planned  during the week

(4)

Actual work done during the last week

(5)

Short fall in the last week 

(6)

Work 

Planned for next week

(7)

No of days remaining for completion as per the weekly plan

1

Re wall towards NH side

100%

34

66

32

 

 

0

0

 0

3

Approach

 Span

 

5

 

5

0

37

-

-

-

-

 

4

Pier cap

2

2

0

46

 0

 0

 0

 0

 0

5

Pile (Rly)pulikakadavuside

4

 

4

0

60

 0

 0

0

6

Pile (Rly)Nhside

4

4

0

60

0

0

0

0

0

6

Piers (Rly)

 

2

2

0

51

 0

 0

 0

 0

 

9

R0AD WORK

{WBM} towards pulikkakadavuside

100%

90

 

0

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

1O

Kerb/handrail  (approach portion)N.H side

200m

Inner kerbconcreting complete for a distance of  25 metres.Handrailposts  concreted for a. distance of 50 metres.Nowork in the last week.

 

Nil

 

 

 

 

 

12

Friction slab  approach portion(N.H side

200m

 

No work in the last week

 

 

 

 

     

 

 

 

 

Material Stocking Status

 

 

 

 

Coarse Aggreagate (m3)

12

21

Remarks

 

Fine Aggreagate(m3)

 15

 12

 .

 

Cement(bag)

 31

 35

 

 

Steel(MT)

 6

35

 

 

 RE blocks

 2150 available at site

 

 

 

 

 

Utility shifting

 

 

 

 

Utilities to be shifted

Status

Remarks

 

 

BSNL

 

 

 

 

KSEB

 nohindrance

 

 

 

KWA

 

 .

 

 

Others

 

No hindrance

 

 

 

 

 

Sl.

No

Date

Activity

1

17-9-2011

Tripod and winch shifting to location P8 (V)

2

19-09-2011

Boring of pile started at P8 (V)

3

20-09-2011

Boring of the pile P8 (V) in progress .Total depth bored =14.7m

 

4

21-09-2011

Boring of the pile P8 (V) in progress .Total depth bored =16m

2.Cage reinforcement  work in progress.

5

 

 

6

  

 

 

 

 

22-9-2011

 

23-9-2011

.1.Cage reinforcement work in progress.

 2.Pile boring depth =17.1m

 

.1.Boring of the pile P8 (V) in progress.Reinforcementworks in progress.

 

 

 

 

 

 

•Piling of P8(V) in progress.
•Concreting of the pile P8(V) planned for next week
 
Back
 
    
CONCRETING OF THE PILE P8-5

    
    
CAGE LOWERING FOR THE PILE CONCRETING AT P8

    
    
CAGE LOWERING AT THE LOCATION P8

    
    
ARRANGEMENT FOR BORING AT LOCATION P8-3

    
 
    
BORING AT THE PILE P8

    
    
BORING AT THE PILE P8

    
    
BORING AT P8-3

    
 
 
 

 

 

 

 

 

 

 

Untitled Document