Prevoius Weekly Reports

   Weekly progress report as on 23.09.2011
    

 

Progress Report For Palakkad Sultanpet ROB for the week ending on 23-09-2011

Si No

Activity Description

Total Quantity

Cumulative progress upto last week

Balance  work up to last week

Cumulative delay in Qty up to last week

Work  planned  during the week

Actual work done during the week

Cumulative delay in Qty up to this week

Work  Planned for next week

No of days remaing for completion as per the weekly plan

Remarks

1

PCC for RAFT MOYAN SIDE

1

1

0

0

0

0

0

0

 

 

2

PCC for RAFT PALAKKAD SCHOOL SIDE

3

3

0

0

0

0

0

0

 

 

3

RAFT PALAKKAD SIDE

1

1

0

0

0

0

0

0

 

 

4

RAFT MOYAN SCHOOL SIDE

3

3

0

0

0

0

0

0

 

 

5

PIER PALAKKAD SIDE

1

1

0

0

0

0

0

0

 

 

6

PIER MOYAN SCHOOL SIDE

3

3

0

0

0

0

0

0

 

 

7

PIER CAP PALAKKAD SIDE

1

1

0

0

0

0

0

0

 

 

8

PIER CAP MOYAN SCHOOL SIDE

3

3

0

0

0

0

0

0

 

 

9

RE/R WALL PALAKKAD  SIDE

100%

62%

38%

0

0.00%

0.00%

0.00%

0.00%

 

 

10

RE/R WALL MOYAN SCHOOL SIDE

100%

48%

52%

0

0.00%

0.00%

0.00%

0.00%

 

 

11

BEAM/SLAB  Staging Palakad  SIDE

4

4

0

0

0

0

0

0

 

 

12

BEAM/SLAB  Bar bending and Fixing Palakad  SIDE

4

3

1

0

1

0*

1

1

 

girder bar bending forP4-RP1 completed

13

BEAM/SLAB  Shuttering  and Concreting Palakad SIDE

4

3

1

0

1

0*

0

1

 

P4-RP1 girder 3 nos casted

14

BEAM/SLAB  Staging Moyan schoolSIDE

5

5

0

0

0

0

0

0

 

 

15

BEAM/SLAB  Bar bending and Fixing Moyan school SIDE

5

5

0

0

0

0

0

0

 

 

16

BEAM/SLAB  Shuttering  and Concreting  Moyan school  SIDE

5

5

0

0

0

0

0

0

 

 

17

BEAM/SLAB PALAKKAD  SIDE

4

3

1

0

0

0

0

1

 

 

18

BEAM/SLAB MOYAN SCHOOL SIDE

5

5

0

0

0

0

0

0

 

 

19

BEAM/SLAB RAILWAY SPAN

7

0

7

1

0

0

1

0

 

 

20

HR/FP/KERB PALAKAD  SIDE

100%

0%

100%

0

0.00%

5.00%

0.00%

5.00%

 

P1-P2 kerb casting completed on both sides

21

HR/FP/KERB NH SIDE

100%

45%

55%

0

0.00%

0.00%

0.00%

0.00%

 

 

22

HR/FP/KERB RAILWAY SPAN

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

 

23

BC/PAINTING

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

 

 

Material Stocking Status

 

Required

Available

Fine aggregate {m³}

10

14

Cement(bag)

450

300

Steel in T

8

81

Coarse aggregate (m3)

 12

 15

 
Back
 
    
BOWSTRING I GIRDER CABLE LAID-20.09.2011

    
    
CABLE LAYING OF BOWSTRING I GIRDER - 20.09.2011

    
    
HANDRAIL CASTING - 21.09.2011

    
    
P1-P2 KERB CASTING - 21.09.2011

    
 
    
P4-RP1 GIRDER CASTING - 21.09.2011

    
    
P1-P2 HAND RAIL FIXING - 23.09.2011

    
    
P4-RP1 DECK SLAB BARBENDING - 23.09.2011

    
 
 
 

 

 

 

 

 

 

 