Work Planned upto 17.04.2010 |
Completed / Progress |
Remarks |
Arrangement for stressing girders |
In progress |
|
Concreting 3 girders |
Completed |
|
Staging work for P3-P4 Span |
Completed |
Road Blocked for P3-P4 span work |
Approval of GAD by railways- follow up to be |
|
Delay in GAD approval
done by contractor
|
Box culvert works (under pass) excavation |
In progress |
Started on 12.04.1 |