   Weekly progress report as on 23.09.2011
    

 

Progress Report For Kainatty ROB for the week ending on 23-09-2011

Si No

Activity Description

Total Quantity

Cumulative progress upto last week

Balance  work up to last week

Cumulative delay in Qty up to last week

Work  planned  during the week

Actual work done during the week

Cumulative delay in Qty up to this week

Work  Planned for next week

No of days remaing for completion as per the weekly plan

Remarks

1

PILE KAINATTY  SIDE

18

18

0

0

0

0

0

0

 

 

2

PILE NADAPURAM SIDE

27

27

0

0

0

0

0

0

 

 

3

PILE CAP KAINATTY SIDE

6

4

2

2

2

0*

2

1

 

Pile cap excavation and PCC at P4 location complete

4

PILE CAP  NADAPURAM SIDE

9

9

0

0

0

0

0

0

 

 

5

PIER KAINATTY  SIDE

6

4

2

2

2

0

2

0

 

 

6

PIER NADAPURAM SIDE

9

8

1

1

1

0

1

0

 

 

7

PIER CAP KAINATTY  SIDE

6

4

2

2

2

0

2

2

 

 

8

PIER CAP NADAPURAM SIDE

9

8

1

1

1

0

1

1

 

 

11

RE/R WALL KAINATTY  SIDE

100%

0%

100%

0

0.00%

0.00%

0.00%

0.00%

 

 

10

RE/R WALL NADAPURAM SIDE

100%

0%

100%

0

0.00%

0.00%

0.00%

0.00%

 

 

12

BEAM/SLAB  Staging Kainatty side

6

3

3

3

1

0

3

0

 

 

13

BEAM/SLAB  Bar bending and Fixing Kainatty side

6

3

3

3

1

0

3

0

 

 

14

BEAM/SLAB  Shuttering  and Concreting  Kainatty side

6

3

3

2

1

0

2

0

 

 

15

BEAM/SLAB  Staging Nadapuram side

9

5

4

3

0

1

2

0

 

P8-P9 staging work completed

16

BEAM/SLAB  Bar bending and Fixing Nadapuram side

9

3

6

3

1

1

2

0

 

AP2-P13 slab reinf complete,P10-P11 girder reinf complete

17

BEAM/SLAB  Shuttering  and Concreting  Nadapuram side

9

3

6

2

1

0*

2

1

 

AP2-P13 girder concrete complete

18

BEAM/SLAB KAINATTY  SIDE

6

3

3

0

0

0

0

0

 

 

19

BEAM/SLAB NADAPURAM SIDE

9

3

6

0

0

0

0

0

 

 

20

HR/FP/KERB KAINATTY  SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

 

21

HR/FP/KERB NADAPURAM SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

 

22

BC/PAINTING

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

 

 

 

Availbility of Men

 

 

 

 

 

 

 

Date

17-09-2011

18-09-2011

19-09-2011

20-09-2011

21-09-2011

22-09-2011

23-09-2011

Nof labours

85

85

85

85

85

85

85

 

Material Stocking Status

Available

Remarks

 

 

 

Fine Aggreagate(m3)

25

 

Cement(bag)

350

 

Steel(MT)

24

 

Coarse Aggreagate (m3)

35

 

 
Back
 
    
STEEL WORK AT AP2-P13 SLAB

    
    
SHUTTERING AT P10-P11.

    
    
REPAIRED ROAD

    
    
RAILWAY PIER TO BE CASTED.

    
 
    
P4PILECAP

      
 

 

 

 

 

 

 

 