   Weekly progress report as on 23.09.2011
    

 

Description Progress/Completed Remarks

shifting of utilities

In progress

 

KWA (PHED) sewage line

In progress

complete on Petta side,90% complete on anayara side

KWA Water supply line

In progress

complete on Petta side,90% complete on anayara side

KSEB

In progress

complete on Petta side,90% completed on anayara side

BSNL

In progress

complete on Pettaside,90% completed on nayaraside

 
Back
 
    
LAYING WATER PIPE LINE

    
    
GIVING HOUSE CONNECTION

    
    
ELECTRIC POST SHIFT

    
    
ELECTRIC LINE SHIFT

    
 
    
BSNL POST SHIFT

      
 

 

 

 

 

 

 

 