   Weekly progress report as on 23.09.2011
    

 

Description Progress/Completed Remarks

Pile Concreting (44 nos)

in progress

Done 43 nos

Pile cap

In progress

done 5 nos

Pile load test P7 b

completed

 

Pile cap P9,P8

completed

 

Pier

In progress

done 3nos-P9,P8,P7

Retaining wall RCC footing in puliyanam side

In progress

Done 15m, 15m first lift complete

Dirt wall work

In progress

 

Extension of culvert slab over irrigation canal

completed

 

Drain work

In progress

NH side remaining

KSEB overhead electric line shifting NH side

completed

 

Utilities (KWA) in Puliyanam side

completed

 

Cutting, bending and placing of reinforcement for Base slab and side wall of drain

completed

 

 Excavation for drain 15m . (NH Side)

completed

 

PCC for drain 30.0m . (NH side )

completed

 

 Base slab of drain 35m  (Puliyanam side)

completed

 

 
Back
 
    
PILE CAP P1 RFT WORK (17.09.11)

    
    
PILE P2A CONCRETE (20.09.11)

    
    
PILE CHIPPING A1 (21.09.11)

    
    
PIERCAP P8 RFT WORK (22.09.11)

    
 
    
PILE P2B BORING(23.09.11)

    
    
RC WALL SHUTTERING WORK (23.09.11)

      
 

 

 

 

 

 

 

 