Prevoius Weekly Reports

   Weekly progress report as on 23.09.2011
    

 

Description Progress/Completed Remarks

Pile concreting

In progress

Done 12 nos(P14a ,P11a, P11c complete this week)

Site level survey

completed

 

7 day Cube test

Completed

 

BSNL, KWA site inspection for utility shifting

In progress

BSNL(OFC) made joint inspection

KSEB site inspection for utility shifting

completed

made joint inspection

site clearing in thamarassery area

In progress

 

filling work towards thamarassery side

In progress

almost 25m complete

filling work in piling location

Completed

uptoAP2 area

 
Back
 
    
PILE 11A BORING - 17.09.2011

    
    
PILE 11A CONCERTING - 17.09.2011

    
    
FILLING IN PROGRESS FROM THAMARASSERY SIDE - 22.09.2011

    
    
PILE 14A CONCRETING - 22.09.2011

    
 
    
PILE11C BORING - 22.09.2011

      
 

 

 

 

 

 

 

 