   Weekly progress report as on 23.09.2011
    

Progress Report For Payyannur ROB for the week ending on 23-09-2011

Si No

Activity Description

Total Quantity

Cumulative progress upto last week

Balance  work up to last week

Cumulative delay in Qty up to last week

Work  planned  during the week

Actual work done during the week

Cumulative delay in Qty up to this week

Work  Planned for next week

Remarks

1

PILE THRIKKARIPUR  SIDE

33

33

0

0

0

0

0

0

 

2

PILE EZHIMALA SIDE

27

27

0

0

0

0

0

0

 

3

PILE PAYYANNUR SIDE

27

27

0

0

0

0

0

0

 

4

PILE CAP THRIKKARIPUR  SIDE

11

11

0

0

0

0

0

0

 

5

PILE CAP EZHIMALA SIDE

9

9

0

0

0

0

0

0

 

6

PILE CAP PAYYANNUR SIDE

9

9

0

0

0

0

0

0

 

9

PIER THRIKKARIPUR  SIDE

11

11

0

0

0

0

0

0

 

8

PIER EZHIMALA SIDE

9

9

0

0

0

0

0

0

 

9

PIER PAYYANNUR SIDE

9

9

0

0

0

0

0

0

 

10

PIER CAP THRIKKARIPUR  SIDE

11

11

0

0

0

0

0

0

 

11

PIER CAP EZHIMALA SIDE

9

9

0

0

0

0

0

0

 

12

PIER CAP PAYYANNUR SIDE

9

9

0

0

0

0

0

0

 

16

RE/R WALL THRIKKARIPUR  SIDE

100%

45%

55%

0

0.00%

0.00%

0.00%

0.00%

 

17

RE/R WALL EZHIMALA SIDE

100%

45%

55%

0

0.00%

0.00%

0.00%

0.00%

 

18

RE/R WALL PAYYANNUR SIDE

100%

0

100%

0

0.00%

0.00%

100.00%

0.00%

 

19

BEAM/SLAB  Staging Thrikkaripur side

10

9

1

0

0

1

0

0

 

20

BEAM/SLAB  Bar bending and Fixing Thrikkaripur side

10

9

1

0

1

1

0

0

 

21

BEAM/SLAB  Shuttering  and Concreting  Thrikkaripur side

10

9

1

1

1

1

0

0

P9-P10 slab complete

22

BEAM/SLAB  Staging Ezhimala side

8

5

3

2

0

0*

2

0

P13-P14 girder staging complete

23

BEAM/SLAB  Bar bending and Fixing Ezhimala side

8

5

3

2

1

0*

2

0

P13-P14 girder bar bending complete

24

BEAM/SLAB  Shuttering  and Concreting  Ezhimala side

8

5

3

1

0

0

1

1

 

25

BEAM/SLAB  Staging Payyanur side

9

8

1

1

0

0

1

0

 

26

BEAM/SLAB  Bar bending and Fixing Payyanur side

9

8

1

1

0

0

1

0

 

27

BEAM/SLAB  Shuttering  and Concreting Payyanur side

9

8

1

1

0

0

1

0

 

28

BEAM/SLAB THRIKKARIPUR  SIDE

10

9

1

1

1

1

0

0

 

29

BEAM/SLAB EZHIMALA SIDE

8

5

3

1

0

0

1

1

 

30

BEAM/SLAB PAYYANNUR SIDE

9

8

1

1

0

0

1

0

 

31

HR/FP/KERB THRIKKARIPUR  SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

32

HR/FP/KERB EZHIMALA SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

33

HR/FP/KERB PAYYANNUR SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

34

BC/PAINTING

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

 

 

Availbilityof Men

 

 

 

 

 

 

 

Date

17-09-2011

18-09-2011

19-09-2011

20-09-2011

21-09-2011

22-09-2011

23-09-2011

Nof labours

70

0

0

70

70

70

70

 

Material Stocking Status

 

 

 

 

Required

Available

Remarks

Coarse Aggreagate (m3)

 

Available

 

Fine Aggreagate(m3)

 

Available

 

Cement(bag)

600

800

 

Steel(MT)

15

65

 

 
Back
 
    
RAILWAY PILING WORK IP

    
    
P12-P13 DE-SHUTTERING

    
    
P9-P10 SLAB WORK IP

    
    
KERB WORK IP PAYYANNUR SIDE

    
 
    
EZHIMALA SIDE FINAL WORK IP

    
    
DIRT WALL STEEL WORK

      
 

 

 

 

 

 

 

 