   Weekly progress report as on 23.09.2011
    
 

SlNo

Activity –which can be completed without caution

Description

Total Quantity

Cumulative progress up to this week

(1)

Balance  work

(2)

Cumulative delay in weeks after

Spplagmnt

(3)

Work  planned  during the week

(4)

Actual work done during the last week

(5)

Short fall in the last week 

(6)

Work 

Planned for next week

(7)

No of days remaining for completion as per the weekly plan

1

Re wall towards NH side

100%

34

66

32

 

 

0

0

 0

3

Approach

 Span

 

5

 

5

0

37

-

-

-

-

 

4

Pier cap

2

2

0

46

 0

 0

 0

 0

 0

5

Pile (Rly)pulikakadavuside

4

 

4

0

60

 0

 0

0

6

Pile (Rly)Nhside

4

4

0

60

0

0

0

0

0

6

Piers (Rly)

 

2

2

0

51

 0

 0

 0

 0

 

9

R0AD WORK

{WBM} towards pulikkakadavuside

100%

90

 

0

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

1O

Kerb/handrail  (approach portion)N.H side

200m

Inner kerbconcreting complete for a distance of  25 metres.Handrailposts  concreted for a. distance of 50 metres.Nowork in the last week.

 

Nil

 

 

 

 

 

12

Friction slab  approach portion(N.H side

200m

 

No work in the last week

 

 

 

 

     

 

 

 

 

Material Stocking Status

 

 

 

 

Coarse Aggreagate (m3)

12

21

Remarks

 

Fine Aggreagate(m3)

 15

 12

 .

 

Cement(bag)

 31

 35

 

 

Steel(MT)

 6

35

 

 

 RE blocks

 2150 available at site

 

 

  

 

Utility shifting

 

 

 

 

Utilities to be shifted

Status

Remarks

 

 

BSNL

 

 

 

 

KSEB

 nohindrance

 

 

 

KWA

 

 .

 

 

Others

 

No hindrance

 

 

  

 

 Climate and Labours

 

DATE

17-9-2011

19-9-2011

20-9-2011

21-9-2011

22-9-2011

23-9-2011

Weather

cloudy

gloomy

gloomy

gloomy

cloudy

cloudy

Labour

16

13

13

13

13

13

 

Daily Activity Report

Sl.

No

Date

Activity

1

17-9-2011

Tripod and winch shifting to location P8 (V)

2

19-09-2011

Boring of pile started at P8 (V)

3

20-09-2011

Boring of the pile P8 (V) in progress .Total depth bored =14.7m

 

4

21-09-2011

Boring of the pile P8 (V) in progress .Total depth bored =16m

2.Cage reinforcement  work in progress.

5

 

 

 6

  

 

 

 

 

22-9-2011

  23-9-2011

1.Cage reinforcement work in progress.

 2.Pile boring depth =17.1m

 

.1.Boring of the pile P8 (V) in progress.Reinforcementworks in progress.

 

 

 

 

 •Piling of P8(V) in progress.

•Concreting of the pile P8(V) planned for next week 
 
Back
 
    
PILING ARRANGEMENT FOR THE PILE P8(V) - 17.09.2011

    
    
BORING OF THE PILE P8 (V) IN PROGRESS - 19.09.2011

    
    
BORING OF THE PILE P8(V) IN PROGRESS - 20.09.2011

    
    
BORING OF THE PILE P8(V) - 21.09.2011

    
 
    
BORING OF THE PILE P8 (V) - 22.09.2011

    
    
BORING OF THE PILE P8(V) IN PROGRESS - 23.09.2011.JPG

      
 

 

 

 

 

 

 

 