Work Planned upto 24/04/2010 |
Completed / Progress |
Remarks |
P3-P4 Span |
|
|
Stressing girders |
Completed |
|
Concreting 3 girders |
Completed |
|
Staging work for P3-P4 Span |
Completed |
Road Blocked for P3-P4 span work |
Approval of GAD by railways- follow up to be |
|
Delay in GAD approval |
done by contractor |
|
|
Box culvert works (under pass) excavation |
Completed |
Started on 12.04.10 |
PCC |
Completed |
|
Bar bending |
In progress |
|