   Weekly progress report as on 23.09.2011
    
 

Revised Progress Report For Ponnurunni ROB for the week ending on 22-09-2011

Si No

Activity Description

Total Quantity

Cumulative progress upto 22.09.11

Balance  work up to 22.09.11

Cumulative delay in Qty up to 22.09.11

Work  planned  during the week

Actual work done during the week

delay in Qty up to this week

Work  Planned for next week

No of days remaing for completion as per the weekly plan

Remarks

1

PILE  Palarivattom side(Approach portion)

31

28

3

0

0

0

0

0

kwa line to be shifted

KWA & KSEB SERVICE LINES TO BE SHIFTED FOR RESUMING THE PILING WORKS. RAILWAY SIGNAL AND RAIL TEL CABLES TO SHIFTED FOR TAKING UP WORKS AT RP1.

2

PILE Palarivattom side(railway portion)

6

0

6

0

0

0

0

0

"      "

3

PILE vytilla side(Approach portion)

42

0

42

0

0

0

0

0

"      "

4

PILE vytilla side(railway portion)

6

0

6

0

0

0

0

0

"      "

5

PILE CAP Palarivattom side(Approach portion)

8

7

1

1

1

1

0

0

"      "

A2, P15, P14, P13,  P12,  P11 & P10-- 8th Pilecap (P9) can be done only after shifting KWA line.

6

PILE CAP Palarivattomside(railway portion)

1

0

1

0

0

0

0

0

"      "

 

7

PILE CAP vytilla side(Approach portion)

9

0

9

0

0

0

0

0

"      "

 

8

PILE CAP vytilla side(railway portion)

1

0

1

0

0

0

0

0

"      "

 

9

PIER Palarivattom side(Approach portion)

8

7

1

0

3

1

0

0

 

A2, P15, P14, P13,  P12,  P11, P10

10

PIER Palarivattomside(railway portion)

1

0

1

0

0

0

0

0

 

 

11

PIER Vytilla side(Approach portion)

9

0

9

0

0

0

0

0

"      "

 

12

PIER vytilla side(railway portion)

1

0

1

0

0

0

0

0

"      "

 

13

PIER  CAP Palarivattom side(Approach portion)

8

5

3

0

0

0

2

2

 

P15, P14, A2, P13, P12

14

PIER CAP Palarivattomside(railway portion)

1

0

1

0

0

0

0

0

 

 

15

PIER CAP  Vytilla side(Approach portion)

9

0

9

0

0

0

0

0

"      "

 

16

PIER CAP vytilla side(railway portion)

1

0

1

0

0

0

0

0

"      "

 

17

RE WALL PANEL

355

355

0

0

0

1

0

0

0

  

 

 

 

Labour Report              
               
Date 16.09.11 17.09.11 18.09.11 19.09.11 20.09.11 21.09.11 22.09.11
Day Fri Sat Sun Mon Tue Wed Thurs
Climate sunny sunny sunny sunny sunny sunny sunny
No.of labours 30 35 7 1 36 31 37 

 

 

Availability of Material

 

 

Materials

Required for week ending on 29.09.11

Available as on 22.09.2011

Fine aggregate(M3)

Ready Mix Concrete

Coarse aggregate(M3)

Cement(BAG)

Steel(TONN)

2

24.2 

 
Back
 
    
GIRDER SHUTTERING A2 P15 - 17.09.2011

    
    
PEDESTAL CONCRETING P14 - 20.09.2011

    
    
KWA WORK IN PROGRESS - 21.09.2011

    
    
GIRDER REINFORCEMENT A2 P15 - 22.09.2011

    
 
    
TRIAL MIS M40 FOR GIRDER AT RMC PLANT, KUMBALAM - 22.09.2011

      
 

 

 

 

 

 

 

 