Prevoius Weekly Reports

   Weekly progress report as on 23.09.2011
    
   
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE SHORNUR  SIDE 9 9       Completed        
2 PILE M.C SIDE 36 36       Completed        
3 PILE CAP SHORNUR SIDE 3 3       Completed        
4 PILE CAP  M.C SIDE 12 12       Completed        
5 PIER SHORNUR  SIDE 3 3       Completed        
6 PIER M.C SIDE 12 12       Completed        
7 PIER CAP SHORNUR  SIDE 3 3       Completed        
8 PIER CAP M.C SIDE 12 12       Completed        
9 RE/R WALL SHORNUR SIDE 100% 40 60% 0 10.00% 4.00% 46.00% 10.00% 0 concreting of the 2nd stage of RCC wall in the "C" portion in the shornur side completed
10 RE/R WALL M.C SIDE 100% 9 91% 0 0.00% 0.00% 2.00% 0.00% 0  
11 BEAM/SLAB SHORNUR  SIDE 3 2 1 0 0 0 0 0 0  
12 BEAM/SLAB M.C SIDE 12 10 2 0 0 0 1 1 0 beam shuttering work of the span P3-P4 in progress.beam reinforcement completed
13 HR/FP/KERB SHORNUR  SIDE 100% 50 50% 0 0.00% 0.00% 0.00% 0.00% 0 days  
14 HR/FP/KERB M.C SIDE 100% 46 54% 0 5.00% 5.00% 0.00% 10.00%   inner kerb concreting of two more spans completed ..ie (P11-P12,P10-P11 and one side of P9-P10 Handrail fixing of one span(P6-P7 and one side of P6-P5 completed.Outer kerb  of P5-P4 complete and one side of P7-P8
15 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%     

 

 

Availbility of Men              
Date 17-9-2011 18-9-2011 19-9-2011 20-9-2011 21-9-2011 22-9-2011 23-9-2011
Nof labours 54 35 47 44 46 48 46 

 

 

Material Stocking Status          
  Required Available Remarks    
Fine aggregate {cft} 650 400 stock will be replendished     
Cement(bag) 650 150 stock will be replendished today    
Steel inT 11 14      
Coarse Aggreagate (cft) 430 400       

 

Utility shifting    
Utilities to be shifted   Remarks
BSNL COMPLETED  
KSEB COMPLETED  
KWA COMPLETED  
Others COMPLETED   

 

 
Back
 
    
INNER KERB CONCRETING AT P11-P12 - 17.09.2011

    
    
OUTER KERB CONCRETING AT P7-P8 - 18.09.2011

    
    
BOTTOM SHUTTER SETTING AND LEVELLING AT P3-P4 - 19.08.2011

    
    
GIRDER REINFORCEMENT AT P3-P4 IN PROGRESS - 20.09.2011

    
 
    
GIRDER REINFORCEMENT IN PROGRESS AT P3-P4 - 21.09.2011

    
    
RCC WALL CONCRETING - 22.09.2011

    
    
BEAM SHUTTERING WORK AT P3-P4 IN PROGRESS - 23.09.2011

    
 
 
 

 

 

 

 

 

 

 