   Weekly progress report as on 16.09.2011
    

Si No

Activity Description

Total Quantity

Cumulative progress upto last week

Balance  work up to last week

Cumulative delay in Qty up to last week

Work  planned  during the week

Actual work done during the week

Cumulative delay in Qty up to this week

Work  Planned for next week

No of days remaing for completion as per the weekly plan

Remarks

1

PILE KAINATTY  SIDE

18

18

0

0

0

0

0

0

 

 

2

PILE NADAPURAM SIDE

27

27

0

0

0

0

0

0

 

 

3

PILE CAP KAINATTY SIDE

6

4

2

2

2

0

2

2

 

 

4

PILE CAP  NADAPURAM SIDE

9

9

0

0

0

0

0

0

 

 

5

PIER KAINATTY  SIDE

6

4

2

2

2

0

2

2

 

 

6

PIER NADAPURAM SIDE

9

8

1

1

1

0

1

1

 

 

7

PIER CAP KAINATTY  SIDE

6

4

2

2

2

0

2

2

 

 

8

PIER CAP NADAPURAM SIDE

9

8

1

1

1

0

1

1

 

 

11

RE/R WALL KAINATTY  SIDE

100%

0%

100%

0

0.00%

0.00%

0.00%

0.00%

 

 

10

RE/R WALL NADAPURAM SIDE

100%

0%

100%

0

0.00%

0.00%

0.00%

0.00%

 

 

12

BEAM/SLAB  Staging Kainatty side

6

3

3

3

1

0

3

0

 

 

13

BEAM/SLAB  Bar bending and Fixing Kainatty side

6

3

3

3

1

0

3

0

 

 

14

BEAM/SLAB  Shuttering  and Concreting  Kainatty side

6

3

3

2

1

0

2

0

 

 

15

BEAM/SLAB  Staging Nadapuram side

9

5

4

3

0

0

3

0

 

 

16

BEAM/SLAB  Bar bending and Fixing Nadapuram side

9

3

6

3

0

0

3

1

 

P10-P11,AP2-P13 reinforcement for girder complete

17

BEAM/SLAB  Shuttering  and Concreting  Nadapuram side

9

3

6

2

1

0*

2

1

 

AP2-P13 girder concrete complete

18

BEAM/SLAB KAINATTY  SIDE

6

3

3

0

0

0

0

0

 

 

19

BEAM/SLAB NADAPURAM SIDE

9

3

6

0

0

0

0

0

 

 

20

HR/FP/KERB KAINATTY  SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

 

21

HR/FP/KERB NADAPURAM SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

 

22

BC/PAINTING

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

 

 

Availbility of Men 

 

Date

10-09-2011

11-09-2011

12-09-2011

13-09-2011

14-09-2011

15-09-2011

16-09-2011

Nof labours

85

85

85

85

85

85

85

 

Material Stocking Status

 

 

Available

 

 

Fine Aggreagate(m3)

6

Cement(bag)

400

Steel(MT)

25

Coarse Aggreagate (m3)

12

 
Back
 
    
CONCRETING OF GIRDER AP2-P13 - 14.09.2011

    
    
CONCRETING OF AP2-P13 - 15.09.2011

    
    
STAGING OF P10-P11 - 15.09.2011

      
 

 

 

 

 

 

 

 