Description |
Progress |
Remarks |
Pile concreting
|
in progress
|
Done 24nos
|
P6b boring work
|
In progress
|
21 m complete
|
AP2,P15,P13 consolidation and marking
|
completed
|
|
Building demolition at P2 location
|
In progress
|
|
Building demolition at P3,P4 location
|
In progress
|
removal of debris in progress
|
building demolition at P4 location
|
completed
|
|
Demolition of 2 shops in P6 location
|
Completed
|
|
KSEB utility shifting near AP2
|
Completed
|
|
BSNL cable shifting
|
In progress
|
|
pile chipping at AP2
|
In progress
|
water logging due to rain causes delay
|