Work Planned upto 1/5/2010 |
Complete / Progress |
Remarks |
P3-P4 Span |
|
|
Stressing girders |
Completed |
|
Concreting 3 girders |
Completed |
|
Staging work for P3-P4 Span |
Completed |
Road blocked for P3-P4 span work |
Approval Of GAD by railways-follow up to be |
|
Delay in GAD approval |
done by contractor |
|
|
Box culvert work (under pass) excavation |
Completed |
Started on 12/4/10 |
PCC |
Completed |
|
Bar bending & fixing |
In progress |
|