   Weekly progress report as on 16.09.2011
    
Description Completed/Progress Remarks

Pile concreting

In progress

Done 9 nos(P11b,P14b,P14c complete this week)

Site level survey

completed

 

7 day Cube test

Completed

 

BSNL, KWA site inspection for utility shifting

In progress

BSNL(OFC) made joint inspection

KSEB site inspection for utility shifting

completed

made joint inspection

site clearing in thamarassery area

In progress

 

filling work towards thamarassery side

In progress

 

filling work in piling location

Completed

uptoAP2 area

 
Back
 
    
PILING SITE VIEW FROM MUTHAMBI SIDE - 13.09.2011

    
    
PILE 14B CONCRETING - 13.09.2011

    
    
PILE 14B CAGE LOWEING - 13.09.2011

    
    
PILE 11B BORING - 13.09.2011

    
 
    
PILE 11B CONCRETING - 15.09.2011

    
    
PILE 11B CONCRETING & 11C BORING - 15.09.2011

    
    
PILE 14C BORING - 15.09.2011

    
 
 
 

 

 

 

 

 

 

 