   Weekly progress report as on 16.09.2011
    
 Description Completed/Progress   Remarks

Pile Concreting (42 nos)

in progress

  Done 40 nos(P1a pile complete this week )

Pile cap

In progress

  done 5 nos

Pile load test P7 b

completed

 

Pile cap P9,P8

completed

 

Pier

In progress

done 3nos-P9,P8,P7

Retaining wall RCC footing in puliyanam side

In progress

Done 15m, 15m first lift complete

Dirt wall work

In progress

 

Extension of culvert slab over irrigation canal

completed

 

Drain work

In progress

NH side remaining

KSEB overhead electric line shifting NH side

completed

 

Utilities (KWA) in Puliyanam side

completed

 

Cutting, bending and placing of reinforcement for Base slab and side wall of drain

completed

 

 Excavation for drain 15m . (NH Side)

completed

 

PCC for drain 30.0m . (NH side )

completed

 

 Base slab of drain 35m  (Puliyanam side)

completed

 

 
Back
 
    
P7 PIER CONCRETE -12.09.2011

    
    
P3 HAUNCH CONCRETE - 13.09.2011

    
    
P3 PIER CONCRETE - 13.09.2011

    
    
PILE A1B CONCRETE - 15.09.2011

    
 
 
 

 

 

 

 

 

 

 