   Weekly progress report as on 16.09.2011
    

Progress Report For Payyannur ROB for the week ending on 16-09-2011

Si No

Activity Description

Total Quantity

Cumulative progress upto last week

Balance  work up to last week

Cumulative delay in Qty up to last week

Work  planned  during the week

Actual work done during the week

Cumulative delay in Qty up to this week

Work  Planned for next week

Remarks

1

PILE THRIKKARIPUR  SIDE

33

33

0

0

0

0

0

0

 

2

PILE EZHIMALA SIDE

27

27

0

0

0

0

0

0

 

3

PILE PAYYANNUR SIDE

27

27

0

0

0

0

0

0

 

4

PILE CAP THRIKKARIPUR  SIDE

11

11

0

0

0

0

0

0

 

5

PILE CAP EZHIMALA SIDE

9

9

0

0

0

0

0

0

 

6

PILE CAP PAYYANNUR SIDE

9

9

0

0

0

0

0

0

 

9

PIER THRIKKARIPUR  SIDE

11

11

0

0

0

0

0

0

 

8

PIER EZHIMALA SIDE

9

9

0

0

0

0

0

0

 

9

PIER PAYYANNUR SIDE

9

9

0

0

0

0

0

0

 

10

PIER CAP THRIKKARIPUR  SIDE

11

11

0

0

0

0

0

0

 

11

PIER CAP EZHIMALA SIDE

9

9

0

0

0

0

0

0

 

12

PIER CAP PAYYANNUR SIDE

9

9

0

0

0

0

0

0

 

16

RE/R WALL THRIKKARIPUR  SIDE

100%

45%

55%

0

0.00%

0.00%

0.00%

0.00%

 

17

RE/R WALL EZHIMALA SIDE

100%

45%

55%

0

0.00%

0.00%

0.00%

0.00%

 

18

RE/R WALL PAYYANNUR SIDE

100%

0

100%

0

0.00%

0.00%

100.00%

0.00%

 

19

BEAM/SLAB  Staging Thrikkaripur side

10

9

1

0

0

0*

0

0

P9-P10 girder staging completed

20

BEAM/SLAB  Bar bending and Fixing Thrikkaripur side

10

9

1

1

1

0*

1

0

P9-P10 girder bar bending completed

21

BEAM/SLAB  Shuttering  and Concreting  Thrikkaripur side

10

8

2

2

1

1

1

1

P7-P8 slab concrete coplete

22

BEAM/SLAB  Staging Ezhimala side

8

5

3

2

0

0*

2

0

P13-P14 girder staging complete

23

BEAM/SLAB  Bar bending and Fixing Ezhimala side

8

4

4

3

1

1

3

0

 

24

BEAM/SLAB  Shuttering  and Concreting  Ezhimala side

8

4

4

1

1

1

1

0

P12-P13 slab complete

25

BEAM/SLAB  Staging Payyanur side

9

8

1

1

0

0

1

0

 

26

BEAM/SLAB  Bar bending and Fixing Payyanur side

9

8

1

1

0

0

1

0

 

27

BEAM/SLAB  Shuttering  and Concreting Payyanur side

9

8

1

1

0

0

1

0

 

28

BEAM/SLAB THRIKKARIPUR  SIDE

10

8

2

2

0

1

2

1

 

29

BEAM/SLAB EZHIMALA SIDE

8

4

4

2

0

1

2

0

 

30

BEAM/SLAB PAYYANNUR SIDE

9

8

1

1

0

0

1

0

 

31

HR/FP/KERB THRIKKARIPUR  SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

32

HR/FP/KERB EZHIMALA SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

33

HR/FP/KERB PAYYANNUR SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

34

BC/PAINTING

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

 

Availbility of Men 

Date

10-09-2011

11-09-2011

12-09-2011

13-09-2011

14-09-2011

15-09-2011

16-09-2011

Nof labours

80

80

80

80

80

80

80

 

Material Stocking Status

 

Required

Available

Remarks

 

Coarse Aggreagate (m3)

 

Available

 

 

Fine Aggreagate(m3)

 

Available

 

 

Cement(bag)

600

800

 

 

Steel(MT)

15

85

 

 

 
Back
 
    
VIEW TOWARDS PAYYANNUR SIDE

    
    
VIEW FROM T JN TO P17

    
    
PASSAGE FOR 2&3 WHEELERS

    
    
P9-10 GIRDER STEEL WORKS

    
 
    
P7-8 SLAB CONCRETING

    
    
KERB CONCRETING

    
    
EZHIMALA SIDE VIEW FROM P17

    
 
 
 

 

 

 

 

 

 

 