   Weekly progress report as on 16.09.2011
    

SlNo

Activity –which can be completed without caution

Description

Total Quantity

Cumulative progress up to this week

(1)

Balance  work

(2)

Cumulative delay in weeks after

Spplagmnt

(3)

Work  planned  during the week

(4)

Actual work done during the last week

(5)

Short fall in the last week 

(6)

Work 

Planned for next week

(7)

No of days remaining for completion as per the weekly plan

1

Re wall towards NH side

100%

34

66

32

 

 

0

0

 0

3

Approach

 Span

 

5

 

5

0

37

-

-

-

-

 

4

Pier cap

2

2

0

46

 0

 0

 0

 0

 0

5

Pile (Rly)pulikakadavuside

4

 

4

0

60

 0

 0

0

6

Pile (Rly)Nhside

4

4

0

60

0

0

0

0

0

6

Piers (Rly)

 

2

2

0

51

 0

 0

 0

 0

 

9

R0AD WORK

{WBM} towards pulikkakadavuside

100%

90

 

0

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

1O

Kerb/handrail  (approach portion)N.H side

200m

Inner kerbconcreting complete for a distance of  25 metres.Handrailposts  concreted for a. distance of 50 metres.Nowork in the last week.

 

Nil

 

 

 

 

 

12

Friction slab  approach portion(N.H side

200m

 

friction slab  completed upto60 m total.Nowork in the last week.

 

 

 

 

     

 

 

 

 

Activities which cannot be completed without caution

1

Pile 10Nos

Pier -2Nos

Pier Cap-2 Nos

Deck -3slab

 

 

Material Stocking Status

 

 

Coarse Aggreagate (m3)

12

21

Fine Aggreagate(m3)

 15

 19

Cement(bag)

 31

 30

Steel(MT)

 6

43

 RE blocks

 2150 available at site

 

 

Utility shifting

 

Utilities to be shifted

Status

BSNL

 

KSEB

 nohindrance

KWA

 

Others

 

No hindrance

 

 

Climate & Labour details

 

DATE

12-09-2011

13-09-2011

14-09-2011

15-9-2011

16-9-2011

Weather

cloudy

Rainy

rainy

rainy

cloudy

No of labours

3

5

5

0

12

 

DAILY ACTIVITY REPORT

 

Sl.

No

Date

Activity

1

3-9-2011 to 12-09-2011

 

NO WORK

2

13-09-2011

Joint inspection of the railway portion of korattyrob by railways and RBDCK

3

14-09-2011

1 .”CAUTION “ obtained for 20 kmsfor korattyat 9.35am

Arrangement for “CAUTION” works and setting up the caution board

 

4

15-09-2011

1.No work due to heavy rain

5

 

 

 

 

 

  

 

 

 

 

16-9-2011

.1.Commencement of works for the railway span under “CAUTION “ board.

Piling work commencement near the railway span.

 

 

 

 

 

 
Back
 
    
CAUTION BOARDS FOR THE RAILWAY SPAN WORK - 12.09.2011

    
    
JOINT INSPECTION BY RBDCK AND RAILWAYS - 13.09.2011

    
    
SETTING UP OF CAUTION BOARDS NER THE RAILWAY TRACK - 14.09.2011

    
    
FIXING OF CAUTION BOARDS - 14.09.2011

    
 
    
CAUTION BOARDS FIXING - 14.09.2011

    
    
COMMENCEMENT OF PILING FOR RAILWAY SPAN - 16.09.2011

      
 

 

 

 

 

 

 

 