   Weekly progress report as on 16.09.2011
    

Revised Progress Report For Mulankunnathukavu ROB for the week ending on 16-9-2011

 

Si No

Activity Description

Total Quantity

Cumulative progress upto last week

Balance  work up to last week

Cumulative delay in Qty up to last week

Work  planned  during the week

Actual work done during the week

Cumulative delay in Qty up to this week

Work  Planned for next week

No of days remaing for completion as per the weekly plan

Remarks

1

PILE SHORNUR  SIDE

9

9

 

 

 

Completed

 

 

 

 

2

PILE M.C SIDE

36

36

 

 

 

Completed

 

 

 

 

3

PILE CAP SHORNUR SIDE

3

3

 

 

 

Completed

 

 

 

 

4

PILE CAP  M.C SIDE

12

12

 

 

 

Completed

 

 

 

 

5

PIER SHORNUR  SIDE

3

3

 

 

 

Completed

 

 

 

 

6

PIER M.C SIDE

12

12

 

 

 

Completed

 

 

 

 

7

PIER CAP SHORNUR  SIDE

3

3

 

 

 

Completed

 

 

 

 

8

PIER CAP M.C SIDE

12

12

 

 

 

Completed

 

 

 

 

9

RE/R WALL SHORNUR SIDE

100%

40

60%

0

5.00%

0.00%

42.00%

10.00%

0

Raft foundation completed at one side and the "C" portion. Total earthwaork excavation completed upto 50metres.No work done during last week.

10

RE/R WALL M.C SIDE

100%

9

91%

0

0.00%

0.00%

2.00%

0.00%

0

 

11

BEAM/SLAB SHORNUR  SIDE

3

2

1

0

0

0

0

0

0

 

12

BEAM/SLAB M.C SIDE

12

9

3

0

1

1

1

0

0

concreting of the beam and deck slab of P5-P4 completed . Staging work of P3-P4 completed upto 90%

13

HR/FP/KERB SHORNUR  SIDE

100%

50

50%

0

0.00%

0.00%

0.00%

0.00%

0 days

handrail fixing, outer kerb and expansion joint concreting  completed for two spans  in the shornur side

14

HR/FP/KERB M.C SIDE

100%

36

64%

0

5.00%

5.00%

0.00%

10.00%

 

inner kerb concreting of two spans completed (AP2-P13,P13-P12).handrail fixing completed for six spans in the M.C side

15

BC/PAINTING

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

 

 

Availbility of Men

 

Date

09-04-2011

09-06-2011

09-07-2011

09-12-2011

13-9-2011

14-9-2011

15-9-2011

16-9-2011

Nof labours

58

59

59

60

57

58

57

59

 

Material Stocking Status  

 

Date

09-04-2011

09-06-2011

09-07-2011

09-12-2011

13-9-2011

14-9-2011

15-9-2011

16-9-2011

Nof labours

58

59

59

60

57

58

57

59

 

Utility shifting

Utilities to be shifted

 

Remarks

 

 

BSNL

COMPLETED

 

 

 

KSEB

COMPLETED

 

 

 

KWA

COMPLETED

 

 

 

Others

COMPLETED

 

 

TOTAL NUMBER OF HANDRAILS CASTED IS  76 uptothis date

 
Back
 
    
INNER KERB CONCRETING AT AP2-P13 - 12.09.2011

    
    
INNER KERB SHUTTERING AT P12-P13 - 13.09.2011

    
    
INNER KERB CONCRETING AT P12-P13 - 14.09.2011

    
    
HAND RAIL POST CONCRETING AT P7-P6 - 14.09.2011

    
 
    
DECK SLAB CONCRETING AT P5-P4 - 15.09.2011

    
    
STAGING WORK AT P3-P4 - 16.09.2011

      
 

 

 

 

 

 

 

 