Revised Progress Report For Mulankunnathukavu ROB for the week ending on 16-9-2011
Si No
Activity Description
Total Quantity
Cumulative progress upto last week
Balance work up to last week
Cumulative delay in Qty up to last week
Work planned during the week
Actual work done during the week
Cumulative delay in Qty up to this week
Work Planned for next week
No of days remaing for completion as per the weekly plan
Remarks
1
PILE SHORNUR SIDE
9
Completed
2
PILE M.C SIDE
36
3
PILE CAP SHORNUR SIDE
4
PILE CAP M.C SIDE
12
5
PIER SHORNUR SIDE
6
PIER M.C SIDE
7
PIER CAP SHORNUR SIDE
8
PIER CAP M.C SIDE
RE/R WALL SHORNUR SIDE
100%
40
60%
0
5.00%
0.00%
42.00%
10.00%
Raft foundation completed at one side and the "C" portion. Total earthwaork excavation completed upto 50metres.No work done during last week.
10
RE/R WALL M.C SIDE
91%
2.00%
11
BEAM/SLAB SHORNUR SIDE
BEAM/SLAB M.C SIDE
concreting of the beam and deck slab of P5-P4 completed . Staging work of P3-P4 completed upto 90%
13
HR/FP/KERB SHORNUR SIDE
50
50%
0 days
handrail fixing, outer kerb and expansion joint concreting completed for two spans in the shornur side
14
HR/FP/KERB M.C SIDE
64%
inner kerb concreting of two spans completed (AP2-P13,P13-P12).handrail fixing completed for six spans in the M.C side
15
BC/PAINTING
Availbility of Men
Date
09-04-2011
09-06-2011
09-07-2011
09-12-2011
13-9-2011
14-9-2011
15-9-2011
16-9-2011
Nof labours
58
59
60
57
Material Stocking Status
Utility shifting
Utilities to be shifted
BSNL
COMPLETED
KSEB
KWA
Others
TOTAL NUMBER OF HANDRAILS CASTED IS 76 uptothis date