   Weekly report as on 09.09.2011
    
Description Completed/Progress    Remarks
Pile Concreting (42 nos) in progress Done 39 nos(A1a pile complete this week )
Pile cap  In progress done 5 nos  
Pile load test P7 b completed    
Pile cap P9,P8 completed    
Pier  In progress done 3nos-P9,P8,P7  
Retaining wall RCC footing in puliyanam side In progress Done 15m, 15m first lift complete  
Dirt wall work In progress    
Extension of culvert slab over irrigation canal completed    
Drain work  In progress NH side remaining  
KSEB overhead electric line shifting NH side completed    
Utilities (KWA) in Puliyanam side completed    
Cutting, bending and placing of reinforcement for Base slab and side wall of drain  completed    
 Excavation for drain 15m . (NH Side) completed    
PCC for drain 30.0m . (NH side ) completed    
 Base slab of drain 35m  (Puliyanam side)  completed    

 

 