Description |
Completed/Progress |
Remarks |
Pile Concreting (42 nos) |
in progress |
Done 39 nos(A1a pile complete this week ) |
Pile cap |
In progress |
done 5 nos |
|
Pile load test P7 b |
completed |
|
|
Pile cap P9,P8 |
completed |
|
|
Pier |
In progress |
done 3nos-P9,P8,P7 |
|
Retaining wall RCC footing in puliyanam side |
In progress |
Done 15m, 15m first lift complete |
|
Dirt wall work |
In progress |
|
|
Extension of culvert slab over irrigation canal |
completed |
|
|
Drain work |
In progress |
NH side remaining |
|
KSEB overhead electric line shifting NH side |
completed |
|
|
Utilities (KWA) in Puliyanam side |
completed |
|
|
Cutting, bending and placing of reinforcement for Base slab and side wall of drain |
completed |
|
|
Excavation for drain 15m . (NH Side) |
completed |
|
|
PCC for drain 30.0m . (NH side ) |
completed |
|
|
Base slab of drain 35m (Puliyanam side) |
completed |
|
|