Description |
Completed/Progress |
Remarks |
Design and Drawing for Railway span superstructure |
Submitted |
Approval pending with Railways |
RE Wall work NH side |
In progress |
done 65% |
Hand Rail Fixing |
completed |
Approach & bridge portion for Pulikkakadavu side(from P2 onwards) |
Hand Rail Fixing NH side |
In progress |
approach portion 60 m(both left and right). Can not proceed with the work as the RE wall work is not complete. |
Kerb on footpath side approach portion on NH portion |
In progress |
done 55 m |
Foot path slab (Pulikkakadavu) P2- P3 |
In progress |
done 95% |
concreting of Inner kerb P2-P3 |
completed |
|
RE blocks concreting at approach portion on NH side |
completed |
|
Friction slab concrete NH side approach portion |
In progress |
done 50 m, less scope of work due to incompletion of RE WALL |
RE NH side outer kerb (footpath slab side) |
In progress |
done 15 m |
RE NH side inner kerb (footpath slab side) |
In progress |
done 15 m |
Friction slab concrete NH side approach portion reinforcement and shuttering |
|
|
Pre mix macadam (Pulikkakadavu) |
completed |
2 layers completed |
FOOT PATH slab opp school |
In progress |
20 m |
Railway portion |
|
|
Piling work (P1&P2) |
Completed |
|
Piling work (P7&P8) |
pending |
can be taken up only after getting caution as directed by railways |
Pier Cap & pedestal P2 |
completed |
for land portion |
Excavation for lowering of ground level near P7 |
completed |
|
Pile cap P1 |
completed |
|
Pier P1 |
completed |
|
Pier cap P1 |
completed |
dirt wall and pedestal not complete |
P2- P3 Concrete Span |
completed |
|
P2- P3 slab deshuttering |
completed |
|
Fixing of handrail post at P2-P3 |
completed |
|
Second stage stressing AND GROUNTING for P2-P3 |
Completed |
|
Rubble masonry for retaining wall RE wall near P1 (NH side) |
completed |
|
Toll booth work at Pulikakadav side |
In progress |
Foundation complete |