Pile concreting |
Done 24nos |
AP2,P15,P13 consolidation and marking |
|
Building demolition at P2,P3 location |
25% complete |
building demolition at P4 location |
|
Demolition of 2 shops in P6 location |
|
KSEB utility shifting near AP2 |
|
BSNL cable shifting |
|
pile chipping at AP2 |
water logging due to rain causes delay |