Prevoius Weekly Reports

   weekly progress 9.9.2011
    

status of utility shifting

 

 

KWA (PHED) sewage line Shifting of main sewage line
  Completed. House
  Connections of sewage lines are in progress
  KWA Water supply line Shifting of water
  supply line started
  on 29-8-2011 and is in progress 
KSEB Erection of electric posts
  completed. Shifting
  of electric lines is in progress. Shifting
  of Transformer and under ground
  cable work not
  yet started
BSNL Shifting of BSNL
  Underground cable and over head lines has not yet started
 
Back
 
    
KWA WATER LINE SHIFTING IN PROGRESS - 02.09.2011

    
    
SEWAGE LINE SHIFTING IN PROGRESS - 03.09.2011

    
    
PIPE LINE FOR KWA - 08.09.2011

    
    
ELECTRICITY TRANSFORMER - 08.09.2011

    
 
 
 

 

 

 

 

 

 

 