Pile concreting |
In progress |
Done 6 nos(P15a,P15c,P13b.P13a,P15b,P13c) |
Site level survey |
completed |
|
7 day Cube test |
Completed |
|
BSNL, KWA site inspection for utility shifting |
In progress |
BSNL(OFC) made joint inspection |
KSEB site inspection for utility shifting |
completed |
made joint inspection |
site clearing in thamarassery area |
In progress |
|
filling work in piling location |
Completed |
upto AP2 area |
|