Revised Progress Report For Mulankunnathukavu ROB for the week ending on 09-9-2011
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan
1 PILE SHORNUR  SIDE 9 9       Completed    
2 PILE M.C SIDE 36 36       Completed      
3 PILE CAP SHORNUR SIDE 3 3       Completed      
4 PILE CAP  M.C SIDE 12 12       Completed      
5 PIER SHORNUR  SIDE 3 3       Completed      
6 PIER M.C SIDE 12 12       Completed      
7 PIER CAP SHORNUR  SIDE 3 3       Completed      
8 PIER CAP M.C SIDE 12 12       Completed      
9 RE/R WALL SHORNUR SIDE 100% 35 65% 0 5.00% 0.00% 40.00% 10.00% 0
10 RE/R WALL M.C SIDE 100% 9 91% 0 0.00% 0.00% 2.00% 0.00% 0
11 BEAM/SLAB SHORNUR  SIDE 3 2 1 0 0 0 0 0 0
12 BEAM/SLAB M.C SIDE 12 9 2 0 1 0* 2 1  
13 HR/FP/KERB SHORNUR  SIDE 100% 55% 45% 0 0.00% 0.00% 0.00% 0.00% 0 days
14 HR/FP/KERB M.C SIDE 100% 25% 75% 0 4.00% 0*% 4.00% 10.00%  
15 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
16 Deck Slab                  
17 Utility shifting                  
  Availbility of Men                   
  Date 9/3/2011 9/4/2011 9/5/2011 9/6/2011 9/7/2011 9/8/2011 9/9/2011    
  Nof labours 42 55 55 57 52 10 10    
                     
  Material Stocking Status Required Available Remarks            
  Fine aggregate {cft} 650 900              
  Cement(bag) 650 850 no material shortage at site            
  Steel inT 11 13              
  Coarse Aggreagate (cft) 430 750              
  Utility shifting   Remarks              
  Utilities to be shifted COMPLETED                
  BSNL COMPLETED                
  KSEB COMPLETED                
  KWA COMPLETED     TOTAL NUMBER OF HANDRAILS CASTED IS 310 upto this date          
  Others .                
 