   weekly progress 9.9.2011
    

 

Progress Report For Palakkad Sultanpet ROB for the week ending on 09-09-2011
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week 
1 PCC for RAFT MOYAN SIDE 1 1 0 0 0 0 0 0
2 PCC for RAFT PALAKKAD SCHOOL SIDE 3 3 0 0 0 0 0 0
3 RAFT PALAKKAD SIDE 1 1 0 0 0 0 0 0
4 RAFT MOYAN SCHOOL SIDE 3 3 0 0 0 0 0 0
5 PIER PALAKKAD SIDE 1 1 0 0 0 0 0 0
6 PIER MOYAN SCHOOL SIDE 3 3 0 0 0 0 0 0
7 PIER CAP PALAKKAD SIDE 1 1 0 0 0 0 0 0
8 PIER CAP MOYAN SCHOOL SIDE 3 3 0 0 0 0 0 0
9 RE/R WALL PALAKKAD  SIDE 100% 61% 39% 0 0.00% 0.00% 0.00% 0.00%
10 RE/R WALL MOYAN SCHOOL SIDE 100% 48% 52% 0 0.00% 0.00% 0.00% 0.00%
11 BEAM/SLAB  Staging Palakad  SIDE 4 3 1 0 1 1 0 0
12 BEAM/SLAB  Bar bending and Fixing Palakad  SIDE 4 3 1 0 1 0* 1 1
13 BEAM/SLAB  Shuttering  and Concreting Palakad SIDE 4 3 1 0 0 0 0 1
14 BEAM/SLAB  Staging Moyan schoolSIDE 5 5 0 0 0 0 0 0
15 BEAM/SLAB  Bar bending and Fixing Moyan school SIDE 5 5 0 0 0 0 0 0
16 BEAM/SLAB  Shuttering  and Concreting  Moyan school  SIDE 5 5 0 0 0 0 0 0
17 BEAM/SLAB PALAKKAD  SIDE 4 3 1 0 0 0 0 0
18 BEAM/SLAB MOYAN SCHOOL SIDE 5 5 0 0 0 0 0 0
19 BEAM/SLAB RAILWAY SPAN 7 0 7 0 0 0 1 0
20 HR/FP/KERB PALAKAD  SIDE 100% 0% 100% 0 0.00% 0.00% 0.00% 0.00%
21 HR/FP/KERB NH SIDE 100% 30% 70% 0 0.00% 5.00% 0.00% 0.00%
22 HR/FP/KERB RAILWAY SPAN 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%
23 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%
                   
  Note: Progress review done based on the revised Program (rev-01)        
                   
                 
                   
  ROB Sulthanpet, Palakkad                
  Date Barbenders Mechanics/Electricains Helpers Ret. Wall work        
  9/3/2011 22 7 8 16        
  9/4/2011 12 5 8 14        
  9/5/2011 21 7 6 15        
  9/6/2011 16 4 5 -        
  9/7/2011 21 7 22 16        
  9/8/2011 0 0 0 0        
  9/9/2011 0 0 0 0        
                   
               
  Material Stocking Status            
    Required Available            
  Fine aggregate {m³} 4 10            
  Cement(bag) 100 125            
  Steel in T 2 72            
  Coarse aggregate (m3) 5 15            
 