   weekly progress as on 9.9.2011
    

 

Revised Progress Report For Ponnurunni ROB for the week ending on 08-09-2011
Si No  Activity Description  Total Quantity Cumulative progress upto 08.09.11 Balance  work up to 08.09.11 Cumulative delay in Qty up to 08.09.11 Work  planned  during the week  Actual work done during the week  delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan
1 PILE  Palarivattom side(Approach portion) 31 28 3 0 0 0 0 0 kwa line to be shifted
2 PILE Palarivattom side(railway portion) 6 0 6 0 0 0 0 0 "      "
3 PILE vytilla side(Approach portion) 42 0 42 0 0 0 0 0 "      "
4 PILE vytilla side(railway portion) 6 0 6 0 0 0 0 0 "      "
5 PILE CAP Palarivattom side(Approach portion) 8 7 1 1 1 1 0 0 "      "
6 PILE CAP Palarivattomside(railway portion) 1 0 1 0 0 0 0 0 "      "
7 PILE CAP vytilla side(Approach portion) 9 0 9 0 0 0 0 0 "      "
8 PILE CAP vytilla side(railway portion) 1 0 1 0 0 0 0 0 "      "
9 PIER Palarivattom side(Approach portion) 8 7 1 0 3 1 0 0  
10 PIER Palarivattomside(railway portion) 1 0 1 0 0 0 0 0  
11 PIER Vytilla side(Approach portion) 9 0 9 0 0 0 0 0 "      "
12 PIER vytilla side(railway portion) 1 0 1 0 0 0 0 0 "      "
13 PIER  CAP Palarivattom side(Approach portion) 8 4 4 0 0 0 2 2  
14 PIER CAP Palarivattomside(railway portion) 1 0 1 0 0 0 0 0  
15 PIER CAP  Vytilla side(Approach portion) 9 0 9 0 0 0 0 0 "      "
16 PIER CAP vytilla side(railway portion) 1 0 1 0 0 0 0 0 "      "
17 RE WALL PANEL 355 355 0 0 0 1 0 0 0

 

Labour Report              
               
Date 02.09.11 03.09.11 04.09.11 05.09.11 06.09.11 07.09.11 08.09.11
Day Fri Sat Sun Mon Tue Wed Thurs
Climate Sunny Sunny Sunny Sunny Sunny Sunny Sunny 
No.of labours 32 19.5 1 34 33 33 20
Availability of Material               
               
Materials Required for week ending on 15.09.11 Available as on 09.09.2011          
Fine aggregate(M3) Ready Mix Concrete          
Coarse aggregate(M3)          
Cement(BAG)          
Steel(TONN) 4 28.2          

 

 
Back
 
    
GIRDER STAGING A2 P15

    
    
ARRANGEMENT FOR GIRDER A2 P15 STAGING

    
    
SITE CLEARING FOR GIRDER P12 P13 STAGING

    
    
PIPES FOR KWA LINE SHIFTING

    
 
    
PEDESTAL SHUTTERING P15

    
    
GIRDER STAGING A2 P15

      
 

 

 

 

 

 

 

 