Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 7887316
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   weekly progress 2.9.2011
    

Manager  in charge Contact no :9447078783

SlNo

Activity –which can be completed without caution

Description

Total Quantity

Cumulative progress up to this week

(1)

Balance  work

(2)

Cumulative delay in weeks after

Spplagmnt

(3)

Work  planned  during the week

(4)

Actual work done during the last week

(5)

Short fall in the last week 

(6)

Work 

Planned for next week

(7)

No of days remaining for completion as per the weekly plan

Remarks

1

Re wall towards NH side

100%

34

66

32

 

 

0

0

 0

.

3

Approach

 Span

 

5

 

5

0

37

-

-

-

-

 

 

4

Pier cap

2

2

0

46

 0

 1

 0

 0

 0

 DIRT WALL AT P1 NOT COMPLETED

 

 

5

Pile (Rly)pulikakadavuside

4

 

4

0

60

 0

 0

0

 

6

Pile (Rly)Nhside

4

4

0

60

0

0

0

0

0

 

6

Piers (Rly)

 

2

2

0

51

 0

 0

 0

 0

 

 

9

R0AD WORK

{WBM} towards pulikkakadavuside

100%

90

 

0

 

 

 

 

 

 

 

1O

Kerb/handrail  (approach portion)N.H side

200m

Inner kerbconcreting complete for a distance of  25 metres. Handrail posts  concreted for a distance of 50 metres

 

Nil

10 m handrail fixing

20m handrail fixing

       0

 

Balance portion of kerband handrails..

 

 

12

Friction slab  approach portion(N.H side

200m

 

friction slab  completed upto60 m total.Nowork in the last week.

 

 

 

 

      7

 

 

Scope of work for the friction slab is nil  after 60 metres as the RE wall work is not completed.

 

 

Activities which cannot be completed without caution

1

Pile 10Nos

Pier -2Nos

Pier Cap-2 Nos

Deck -3slab 

 

Material Stocking Status

 

 

 

 

Coarse Aggreagate (m3)

0.5

15

Remarks

 

Fine Aggreagate(m3)

 1

 12

 .

 

Cement(bag)

 0

 0

 

 

Steel(MT)

 2

8

 

 

  

Utility shifting

 

 

 

 

Utilities to be shifted

Status

Remarks

 

 

BSNL

 

 

 

 

KSEB

 nohindrance

 

 

 

KWA

 

 .

 

 

Others

 

No hindrance

 

 

  

RE blocks

 2150 available at site

 

 

  

 

DATE

27-08-2011

29-8-2011

30-8-2011

31-8-2011

1-9-2011

02-9-2011

 

Weather

cloudy

Rainy

rainy

cloudy

cloudy

Rainy

 

No of Labours 3 3 3 3 3 3  
 
Back
 
    
PIERCAP P1(31.9.2011).

    
    
PIERCAP P1(29.8.2011)

    
    
PIERCAP P1(27.8.2011).

    
    
PIERCAP P1(1.9.2011).JPG

    
 
    
PIER CAP P1(2.9.2011).

      
 

 

 

 

 

 

 

 

Untitled Document