|
ROB at Koratty
PROGRESS AS ON 15.05.2010 |
Work Planned upto 15/5/2010 |
Completed / Progress |
Remarks |
P3-P4 Span |
|
|
Shuttering work for slab |
In progress |
|
Stressing girders |
Completed |
|
Concreting cross girders |
Completed |
|
Staging work for P3-P4 Span |
Completed |
|
Approval of GAD by railways |
|
GAD approved |
Box culvert works (under pass) excavation |
Completed |
Start on 12/4/10 |
PCC |
Completed |
|
Bar bending and fixing |
In progress |
|
|