ROB at Cheruvathur |
|
|
Pile concreting |
in progress |
Done 24nos |
AP2,P15,P13 consolidation and marking |
completed |
|
Building demolition at P2,P3 location |
In progress |
25% complete |
building demolition at P4 location |
completed |
|
Demolition of 2 shops in P6 location |
In progress |
70% complete |
KSEB utility shifting near AP2 |
Completed |
|
BSNL cable shifting |
In progress |
|
P7b boring work |
completed |
SPT over, concreting started |
pile chipping at AP2 |
started |
water logging due to rain causes delay |