   weekly progress report as on 2.9.11
    

 

Progress Report For Pulianam  ROB for the week ending on 02.09.11  
Sl No   Activity Description   Total Quantity  Cumulative progress upto last week   Balance  work up to last week  Cumulative delay in Qty up to last week  Work  planned  during the week   Actual work done during the week   Cumulative delay in Qty up to this week  Work  Planned for next week   Remarks 
1 Pile towards NH side 26 26 0 0 1 1 0 0 TARGET ACHIEVED
2 Pile towards Puliyanam side 18 14 4 0 4 4 0 3  
3 Pile cap at NH  Side 6 4 2 0 1 2 0 0  
4 Pile Cap at Pulianam side 4 1 3 0 0 0 0 1  
5 RC wall at Puliyanam side 100% 15% 85% 0 5% 5% 0 5%  
6 pier at NH side 5 2 3 0 1 2 0 1  
                     
                     
Date 27.08.2011 29.08.2011 30.08.2011 31.08.2011 01.08.2011 02.08.2011        
Climate RAINY PLEASANT PLEASANT rainy RAINY RAINY        
No.of labours 40 44 38 27 22 22        
                     
                     
availability of material                  
materials Required Available                
Fine aggregate(M3) 6 15                
Coarse aggregate(M3) 10 30                
Cement(BAG) 200 540                
Steel(TONN) 2 40                
 
Back
 
    
RBDCK PROGRESS REPORT(1

    
    
PILECAP P3 CONCRETING(29.08.11).

    
    
PILE P1C CONCRETING(01.09.11

    
    
PILE P1 CONCRETING(29.08.11)

    
 
    
PILE A1F CONCRETING(01.09.11

    
    
PILE A1E CONCRETING(29.08.11

    
    
PILE A1E CONCRETING(29.08.11)

    
 
 
 

 

 

 

 

 

 

 