   weekly p[rogress as on 2.9.2011
    

 

Revised Progress Report For Mulankunnathukavu ROB for the week ending on 02-9-2011  
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE SHORNUR  SIDE 9 9       Completed      
2 PILE M.C SIDE 36 36       Completed        
3 PILE CAP SHORNUR SIDE 3 3       Completed        
4 PILE CAP  M.C SIDE 12 12       Completed        
5 PIER SHORNUR  SIDE 3 3       Completed        
6 PIER M.C SIDE 12 12       Completed        
7 PIER CAP SHORNUR  SIDE 3 3       Completed        
8 PIER CAP M.C SIDE 12 12       Completed        
9 RE/R WALL SHORNUR SIDE 100% 35 65% 0 5.00% 0.00% 42.00% 10.00% 0  
10 RE/R WALL M.C SIDE 100% 9 91% 0 0.00% 0.00% 2.00% 0.00% 0  
11 BEAM/SLAB SHORNUR  SIDE 3 2 1 0 0 0 0 0 0  
12 BEAM/SLAB M.C SIDE 12 9 2 0 1 0 2 1    
13 HR/FP/KERB SHORNUR  SIDE 100% 45% 55% 0 0.00% 10.00% 0.00% 0.00% 0 days handrails for 2 spans complete
14 HR/FP/KERB M.C SIDE 100% 25% 75% 0 4.00% 0.00% 4.00% 0.00%    
15 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
16 Deck Slab                    
17 Utility shifting                     

 

Availbility of Men                 
Date 27-08-2011 28-08-2011 29-08-2011 30-08-2011 ######## 01-09-2011 02-09-2011  
Nof labours 42 55 55 57 52 58 49  
                 
Material Stocking Status Required Available Remarks          
  650 800            
Fine aggregate {cft} 500 600 no material shortage at site          
Cement(bag) 20 15            
Steel inT 430 500            
Coarse Aggreagate (cft)                
                 
Utility shifting   Remarks            
Utilities to be shifted COMPLETED              
BSNL COMPLETED              
KSEB COMPLETED              
KWA COMPLETED     TOTAL NUMBER OF HANDRAILS CASTED IS 310 upto this date        
Others .              
 