Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 7888637
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   weekly progress as on 2.9.2011
    

 

Progress Report For Parappanangadi ROB for the week ending on 02-09-2011
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE CALICUT  SIDE 30 30 0 0 0 0 0 0    
2 PILE NH SIDE 33 33 0 0 0 0 0 0    
3 PILE RAILWAY SPAN 20 0 20 20 0 0 20 0    
4 PILE CAP CALICUT  SIDE 10 10 0 0 0 0 0 0    
5 PILE CAP NH SIDE 11 11 0 0 0 0 0 0    
6 PILE CAP RAILWAY SPAN 4 0 4 3 2 0 4 4    
7 PIER CALICUT  SIDE 10 10 0 0 0 0 0 0    
8 PIER NH SIDE 11 11 0 0 0 0 0 0    
9 PIER RAILWAY SPAN 4 0 4 4 0 0 4 0    
10 PIER CAP CALICUT  SIDE 10 10 0 0 0 0 0 0    
11 PIER CAP NH SIDE 11 11 0 0 0 0 0 0    
12 PIER CAP RAILWAY SPAN 4 0 4 2 0 0 4 0    
13 RE/R WALL CALICUT  SIDE 100% 0.00% 100% 0 0.00% 0.00% 0.00% 0.00%    
14 RE/R WALL NH SIDE 100% 20.00% 80% 0 0.00% 0.00% 0.00% 0.00%    
15 BEAM/SLAB  Staging CALICUT  SIDE 10 7.65 2.35 0 1 0.1 1 1    
16 BEAM/SLAB  Bar bending and Fixing CALICUT  SIDE 10 7 3 0 1 *0 1 1    
17 BEAM/SLAB  Shuttering  and Concreting  Calicut SIDE 10 7 3 0 1 1 0 o   P7-P8 slab complete
18 BEAM/SLAB  Staging NH SIDE 11 8 3 5 1 0 1 1    
19 BEAM/SLAB  Bar bending and Fixing NH  SIDE 11 5 6 4 1 0 1 1    
20 BEAM/SLAB  Shuttering  and Concreting  NH  SIDE 11 8 3 1 1 0 1 1   *  P13-P12 slab complete
21 BEAM/SLAB CALICUT  SIDE 10 7 3 0 1 1 0 0    
22 BEAM/SLAB NH SIDE 11 8 3 0 1 1 0 0    
23 BEAM/SLAB RAILWAY SPAN 3 0 3 0 0 0 0 0    
24 HR/FP/KERB CALICUT  SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
25 HR/FP/KERB NH SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
26 HR/FP/KERB RAILWAY SPAN 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
27 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%     
 
Back
 
    
STAGING WORK IN P8-P9

    
    

    
    
STAGING IN P8-P9..

    
    
SLAB WORK IN P7-P8

    
 
    
SLAB CONCRETING IN P8-P9. (2).

    
    
REINFORCEMENT STARTED IN P8-P9

    
    
REINFORCEMENT STARTED IN P8-P9

    
 
    
LINER DRIVING IN RP-1

    
    
GROUND PREPARATION IN P11-P10

      
 

 

 

 

 

 

 

 

Untitled Document