Progress Report For Kainatty ROB for the week ending on 02-09-2011 |
Si No |
Activity Description |
Total Quantity |
Cumulative progress upto last week |
Balance work up to last week |
Cumulative delay in Qty up to last week |
Work planned during the week |
Actual work done during the week |
Cumulative delay in Qty up to this week |
Work Planned for next week |
No of days remaing for completion as per the weekly plan |
Remarks |
1 |
PILE KAINATTY SIDE |
18 |
18 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
2 |
PILE NADAPURAM SIDE |
27 |
27 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
3 |
PILE CAP KAINATTY SIDE |
6 |
4 |
2 |
2 |
2 |
0 |
2 |
2 |
|
|
4 |
PILE CAP NADAPURAM SIDE |
9 |
8 |
1 |
1 |
1 |
0 |
1 |
1 |
|
|
5 |
PIER KAINATTY SIDE |
6 |
4 |
2 |
2 |
2 |
0 |
2 |
2 |
|
|
6 |
PIER NADAPURAM SIDE |
9 |
8 |
1 |
1 |
1 |
0 |
1 |
1 |
|
|
7 |
PIER CAP KAINATTY SIDE |
6 |
4 |
2 |
2 |
2 |
0 |
2 |
2 |
|
|
8 |
PIER CAP NADAPURAM SIDE |
9 |
8 |
1 |
1 |
1 |
0 |
1 |
1 |
|
|
11 |
RE/R WALL KAINATTY SIDE |
100% |
0% |
100% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
|
10 |
RE/R WALL NADAPURAM SIDE |
100% |
0% |
100% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
|
12 |
BEAM/SLAB Staging Kainatty side |
6 |
3 |
3 |
3 |
1 |
0 |
3 |
1 |
|
|
13 |
BEAM/SLAB Bar bending and Fixing Kainatty side |
6 |
2 |
4 |
3 |
1 |
1 |
2 |
1 |
|
P2-P3 slab reinf complete |
14 |
BEAM/SLAB Shuttering and Concreting Kainatty side |
6 |
2 |
4 |
3 |
1 |
0 |
4 |
1 |
|
|
15 |
BEAM/SLAB Staging Nadapuram side |
9 |
4 |
5 |
3 |
0 |
2 |
3 |
0 |
|
|
16 |
BEAM/SLAB Bar bending and Fixing Nadapuram side |
9 |
3 |
6 |
3 |
0 |
2 |
4 |
1 |
|
|
17 |
BEAM/SLAB Shuttering and Concreting Nadapuram side |
9 |
2 |
7 |
3 |
0 |
1 |
5 |
0 |
|
P11-P12girder complete |
18 |
BEAM/SLAB KAINATTY SIDE |
6 |
2 |
4 |
0 |
0 |
0 |
0 |
0 |
|
P2-P3 girder concrete complete,reinf of slab complete |
19 |
BEAM/SLAB NADAPURAM SIDE |
9 |
2 |
7 |
0 |
0 |
0 |
0 |
0 |
|
|
20 |
HR/FP/KERB KAINATTY SIDE |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
|
21 |
HR/FP/KERB NADAPURAM SIDE |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
|
22 |
BC/PAINTING |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
|