Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 8051113
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   Report as on 02-09-2011
    

 

Progress Report For Kainatty ROB for the week ending on 02-09-2011
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE KAINATTY  SIDE 18 18 0 0 0 0 0 0    
2 PILE NADAPURAM SIDE 27 27 0 0 0 0 0 0    
3 PILE CAP KAINATTY SIDE 6 4 2 2 2 0 2 2    
4 PILE CAP  NADAPURAM SIDE 9 8 1 1 1 0 1 1    
5 PIER KAINATTY  SIDE 6 4 2 2 2 0 2 2    
6 PIER NADAPURAM SIDE 9 8 1 1 1 0 1 1    
7 PIER CAP KAINATTY  SIDE 6 4 2 2 2 0 2 2    
8 PIER CAP NADAPURAM SIDE 9 8 1 1 1 0 1 1    
11 RE/R WALL KAINATTY  SIDE 100% 0% 100% 0 0.00% 0.00% 0.00% 0.00%    
10 RE/R WALL NADAPURAM SIDE 100% 0% 100% 0 0.00% 0.00% 0.00% 0.00%    
12 BEAM/SLAB  Staging Kainatty side 6 3 3 3 1 0 3 1    
13 BEAM/SLAB  Bar bending and Fixing Kainatty side 6 2 4 3 1 1 2 1   P2-P3 slab reinf complete
14 BEAM/SLAB  Shuttering  and Concreting  Kainatty side 6 2 4 3 1 0 4 1    
15 BEAM/SLAB  Staging Nadapuram side 9 4 5 3 0 2 3 0    
16 BEAM/SLAB  Bar bending and Fixing Nadapuram side 9 3 6 3 0 2 4 1    
17 BEAM/SLAB  Shuttering  and Concreting  Nadapuram side 9 2 7 3 0 1 5 0   P11-P12girder complete
18 BEAM/SLAB KAINATTY  SIDE 6 2 4 0 0 0 0 0   P2-P3 girder concrete complete,reinf of slab complete
19 BEAM/SLAB NADAPURAM SIDE 9 2 7 0 0 0 0 0    
20 HR/FP/KERB KAINATTY  SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
21 HR/FP/KERB NADAPURAM SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
22 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%     

 

Availbility of Men                 
Date   27-08-2011 28-08-2011 29-08-2011 30-08-2011 31-08-2011 01-09-2011 02-09-2011
Nof labours   103 103 103 103 103 103 103
                 
Material Stocking Status Required Available Remarks          
                 
Fine Aggreagate(m3) 16 10            
Cement(bag) 500 850            
Steel(MT) 15 30            
Coarse Aggreagate (m3) 25 20            
                 
Utility shifting                
Utilities to be shifted Status Remarks            
BSNL in progress              
KSEB shifted              
KWA shifted              
Others shifted              
                 
                 
 
Back
 
    
P2-P3 STEEL WORK

    
    
EXPANSION JOINT..

    
    
DRAINAGE SPOUTS

    
    
P11-P12 CONCRETE

    
 
    
STAGING WORK OF PIERCAP P2 27.8.2011.

      
 

 

 

 

 

 

 

 

Untitled Document