Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 8053092
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   Report as on 02.09.2011
    

 

Revised Progress Report For Ponnurunni ROB for the week ending on 01-09-2011
Si No  Activity Description  Total Quantity Cumulative progress upto 01.09.11 Balance  work up to 01.09.11 Cumulative delay in Qty up to 01.09.11 Work  planned  during the week  Actual work done during the week  delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE  Palarivattom side(Approach portion) 31 28 3 0 0 0 0 0 kwa line to be shifted KWA & KSEB SERVICE LINES TO BE SHIFTED FOR RESUMING THE PILING WORKS. RAILWAY SIGNAL AND RAIL TEL CABLES TO SHIFTED FOR TAKING UP WORKS AT RP1.
2 PILE Palarivattom side(railway portion) 6 0 6 0 0 0 0 0 "      "
3 PILE vytilla side(Approach portion) 42 0 42 0 0 0 0 0 "      "
4 PILE vytilla side(railway portion) 6 0 6 0 0 0 0 0 "      "
5 PILE CAP Palarivattom side(Approach portion) 8 7 1 1 1 1 0 0 "      " A2, P15, P14, P13,  P12,  P11 & P10-- 8th Pilecap (P9) can be done only after shifting KWA line.
6 PILE CAP Palarivattomside(railway portion) 1 0 1 0 0 0 0 0 "      "  
7 PILE CAP vytilla side(Approach portion) 9 0 9 0 0 0 0 0 "      "  
8 PILE CAP vytilla side(railway portion) 1 0 1 0 0 0 0 0 "      "  
9 PIER Palarivattom side(Approach portion) 8 7 1 0 3 1 0 0   A2, P15, P14, P13,  P12,  P11, P10 
10 PIER Palarivattomside(railway portion) 1 0 1 0 0 0 0 0    
11 PIER Vytilla side(Approach portion) 9 0 9 0 0 0 0 0 "      "  
12 PIER vytilla side(railway portion) 1 0 1 0 0 0 0 0 "      "  
13 PIER  CAP Palarivattom side(Approach portion) 8 4 4 0 0 0 2 2   P15, P14, A2, P13
14 PIER CAP Palarivattomside(railway portion) 1 0 1 0 0 0 0 0    
15 PIER CAP  Vytilla side(Approach portion) 9 0 9 0 0 0 0 0 "      "  
16 PIER CAP vytilla side(railway portion) 1 0 1 0 0 0 0 0 "      "  
17 RE WALL PANEL 355 355 0 0 0 1 0 0 0   

 

                 
  Labour Report              
                 
  Date 26.08.11 27.08.11 28.08.11 29.0811 30.08.11 31.08.11 01.09.11
  Day Fri Sat Sun Mon Tue Wed Thurs
  Climate rainy rainy rainy rainy rainy rainy rainy
  No.of labours 21 20 3.5 22 19 30.5 13
                 
                 
  Availability of Material               
                 
  Materials Required for week ending on 08.09.11 Available as on 02.09.2011          
  Fine aggregate(M3) Ready Mix Concrete          
  Coarse aggregate(M3)          
  Cement(BAG)          
  Steel(TONN) 4 25.2          
 
Back
 
    
SLUMP TESTING

    
    
SHUTTERING PIER CAP P13

    
    
REINFORECEMENT PIER CAP P-13

    
    
PRE CAST SLABS BEING UNLOADED FOR PLACING PROPS FOR GIIRDER A2-P15

    
 
    
CUBE TESTING

    
    
CONCRETING PIER CAP P13

    
    
CONCRETING PIER CAP A-2

    
 
 
 

 

 

 

 

 

 

 