Work Planned upto 06.02.2010 |
Completed/Progress |
Delay |
RE wall works Medical College side |
Started |
Delay by the contractor |
Fixing of panels 60mm length |
In progress |
Delay due to shortage of earth |
Retaining wall on Shornur side |
Completed |
|
Approach slab |
Completed |
|
Friction slab - reinforcement work |
in progress |
|