   06.02.2010
    

ROB at Athani

Work Planned upto 06.02.2010 Completed/Progress Delay
RE wall works Medical College side  Started  Delay by the contractor 
Fixing of panels 60mm length In progress Delay due to shortage of earth
Retaining wall on Shornur side Completed  
Approach slab Completed  
Friction slab - reinforcement work in progress  
 