   weekly progress 26.8.2011
    

 

Revised Progress Report For Mulankunnathukavu ROB for the week ending on 26-8-2011  
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE SHORNUR  SIDE 9 9       Completed      
2 PILE M.C SIDE 36 36       Completed        
3 PILE CAP SHORNUR SIDE 3 3       Completed        
4 PILE CAP  M.C SIDE 12 12       Completed        
5 PIER SHORNUR  SIDE 3 3       Completed        
6 PIER M.C SIDE 12 12       Completed        
7 PIER CAP SHORNUR  SIDE 3 3       Completed        
8 PIER CAP M.C SIDE 12 12       Completed        
9 RE/R WALL SHORNUR SIDE 100% 35 65% 0 5.00% 10.00% 42.00% 10.00% 0  
10 RE/R WALL M.C SIDE 100% 9 91% 0 0.00% 0.00% 2.00% 0.00% 0  
11 BEAM/SLAB SHORNUR  SIDE 3 2 1 0 0 0 0 0 0  
12 BEAM/SLAB M.C SIDE 12 8 4 0 1 1 2 1 20 days P5,P4 staging work 90% completed
13 HR/FP/KERB SHORNUR  SIDE 100% 3 97% 0 1.00% 0.00% 0.00% 0.00% 0 days  
14 HR/FP/KERB M.C SIDE 100% 14% 86% 0 4.00% 10.00% 0.00% 0.00%   hand rails completed on 6 spans 
15 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
16 Deck Slab                    
17 Utility shifting                    
                       
  Availbility of Men                     
  Date 8/20/2011 8/21/2011 8/22/2011 8/23/2011   8/24/2011 8/25/2011 8/26/2011    
  Nof labours 42 55 55 57   52 58 49    
                       
  Material Stocking Status                    
    Required Available Remarks              
  Fine aggregate {cft} 650 1100                
  Cement(bag) 200 1000 no material shortage at site              
  Steel inT 11 30                
  Coarse Aggreagate (cft) 430 540                
                       
  Utility shifting                    
  Utilities to be shifted   Remarks                
  BSNL COMPLETED                  
  KSEB COMPLETED                  
  KWA COMPLETED                  
  Others COMPLETED     TOTAL NUMBER OF HANDRAILS CASTED IS 310 upto this date            
 