Prevoius Weekly Reports

   weekly progress 26.8.2011
    

 

SlNo

Activity –which can be completed without caution

Description

Total Quantity

Cumulative progress up to this week

(1)

Balance  work

(2)

Cumulative delay in weeks after

Spplagmnt

(3)

Work  planned  during the week

(4)

Actual work done during the last week

(5)

Short fall in the last week 

(6)

Work 

Planned for next week

(7)

No of days remaining for completion as per the weekly plan

1

Re wall towards NH side

100%

34

66

32

 

 

0

0

 0

3

Approach

 Span

 

5

 

5

0

37

-

-

-

-

 

4

Pier cap

2

2

0

46

 0

 1

 0

 0

 0

5

Pile (Rly)pulikakadavuside

4

 

4

0

60

 0

 0

0

6

Pile (Rly)Nhside

4

4

0

60

0

0

0

0

0

6

Piers (Rly)

 

2

2

0

51

 0

 0

 0

 0

 

9

R0AD WORK

{WBM} towards pulikkakadavuside

100%

90

 

0

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

1O

Kerb/handrail  (approach portion)N.H side

200m

Inner kerbconcreting complete for a distance of  25 metres. Handrail posts  concreted for a distance of 50 metres

 

Nil

10 m handrail fixing

20m handrail fixing

       0

 

Balance portion of kerband handrails..

 

12

Friction slab  approach portion(N.H side

200m

 

friction slab  completed upto60 m total.Nowork in the last week.

 

 

 

 

      7

 

 

 

 
Back
 
    
PIERCAP P1 RFT WORK(23.8.2011

    
    
PIERCAP P1 CONCRETE(26.8.2011

    
    
PIERCAP CONCRETE AT P1(25.8.2011

    
    
8PIER CAP P1 SHUTTERING WORK(22.8.2011

    
 
    
HANDRAIL WORK AT NH APPROACH(20.8.2011

    
    
HANDRAIL NH SIDE APPROACH(23.8.2011

    
    
HANDRAIL AT NH SIDE(24.8.2011)

    
 
 
 

 

 

 

 

 

 

 