   weekly progress 26.8.2011
    

 

Progress Report For Pulianam  ROB for the week ending on 26.08.2011 
Sl No   Activity Description   Total Quantity  Cumulative progress upto last week   Balance  work up to last week  Cumulative delay in Qty up to last week  Work  planned  during the week   Actual work done during the week   Cumulative delay in Qty up to this week  Work  Planned for next week  
1 Pile towards NH side 26 26 0 0 1 1 0 0
2 Pile towards Puliyanam side 18 10 8 1 4 4 0 4
3 Pile cap at NH  Side 6 2 4 0 1 1 0 1
4 Pile Cap at Pulianam side 4 0 4 0 0 0 0 1
5 RC wall at Puliyanam side 100% 10% 90% 0 5% 5% 0 5%
                   
                   
                   
Date 20.08.2011 22.08.2011 23.08.2011 24.08.2011 25.08.2011 26.08.2011      
Climate RAINY PLEASANT PLEASANT PLEASANT RAINY PLEASANT      
No.of labours 40 42 42 42 42 45      
                   
                   
availability of material                
materials Required Available              
Fine aggregate(M3) 10 15              
Coarse aggregate(M3) 20 30              
Cement(BAG) 350 700              
Steel(TONN) 8 50              
 
Back
 
    
PILECAP P8 CONCRETING (22.08.2011)

    
    
PILECAP P7 RFT WORK (23.08.11

    
    
PILE CAP P3 RFT WORK (20.08.11

    
    
PILE A1D CONCRETE (25.08.11

    
 
    
PIER IST LIFT CONCRETE (24.08.11

    
    
BOTTOM HAUNCH CONCRETE (23.08.11

    
    
P1D PILE CONCRETE (22.08.11

    
 
    
A1C PILE CONCRETE (22.08.11

      
 

 

 

 

 

 

 

 