Prevoius Weekly Reports

   weekly photos as on 26.8.2011
    

 

Revised Progress Report For Ponnurunni ROB for the week ending on 25-08-2011
Si No  Activity Description  Total Quantity Cumulative progress upto 25.08.11 Balance  work up to 25.08.11 Cumulative delay in Qty up to25.08.11 Work  planned  during the week  Actual work done during the week  delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE  Palarivattom side(Approach portion) 31 28 3 0 0 0 0 0 kwa line to be shifted KWA pipes  TO BE SHIFTED FOR RESUMING THE PILING WORKS. RAILWAY SIGNAL AND RAIL TEL CABLES TO SHIFTED FOR TAKING UP WORKS AT RP1.
2 PILE Palarivattom side(railway portion) 6 0 6 0 0 0 0 0 "      "
3 PILE vytilla side(Approach portion) 42 0 42 0 0 0 0 0 "      "
4 PILE vytilla side(railway portion) 6 0 6 0 0 0 0 0 "      "
5 PILE CAP Palarivattom side(Approach portion) 8 7 1 1 1 1 0 0 "      " A2, P15, P14, P13,  P12,  P11 & P10-- 8th Pilecap (P9) can be done only after shifting KWA line.
6 PILE CAP Palarivattomside(railway portion) 1 0 1 0 0 0 0 0 "      "  
7 PILE CAP vytilla side(Approach portion) 9 0 9 0 0 0 0 0 "      "  
8 PILE CAP vytilla side(railway portion) 1 0 1 0 0 0 0 0 "      "  
9 PIER Palarivattom side(Approach portion) 8 7 1 0 3 1 0 0   A2, P15, P14, P13,  P12,  P11, P10 
10 PIER Palarivattomside(railway portion) 1 0 1 0 0 0 0 0    
11 PIER Vytilla side(Approach portion) 9 0 9 0 0 0 0 0 "      "  
12 PIER vytilla side(railway portion) 1 0 1 0 0 0 0 0 "      "  
13 PIER  CAP Palarivattom side(Approach portion) 8 2 6 0 0 0 2 2   P15, P14
14 PIER CAP Palarivattomside(railway portion) 1 0 1 0 0 0 0 0    
15 PIER CAP  Vytilla side(Approach portion) 9 0 9 0 0 0 0 0 "      "  
16 PIER CAP vytilla side(railway portion) 1 0 1 0 0 0 0 0 "      "  
17 RE WALL PANEL 370 354 16 2 12 10 4 12 0  

 

Date 19.08.11 20.08.11 21.08.11 22.0811 23.08.11 24.08.11 25.08.11
Day Fri Sat Sun Mon Tue Wed Thurs
Climate rainy sunny sunny sunny sunny Sunny Sunny
No.of labours 19 21 1 20 23 20 18
Availability of Material               
               
Materials Required for week ending on 25.08.11 Available as on 19.08.2011          
Fine aggregate(M3) Ready Mix Concrete          
Coarse aggregate(M3)          
Cement(BAG)          
Steel(TONN) 1.5 26.7          
 
Back
 
    
REINFORCEMENT PIER CAP A2(24.8.2011

    
    
REINFORCEMENT PIER CAP A2(24.8.2011

    
    
PIER CAP SHUTTERING A2(23.8.2011

    
    
PIER CAP CONCERETING P14(22.8.2011

    
 
    
PANEL CASTING(20.8.2011).

    
    
CABLE SHIFTING AT RP1 BY RAILWAY(24.8.2011

      
 

 

 

 

 

 

 

 