Pile concreting |
in progress |
Done 21nos |
AP2,P15,P13 consolidation and marking |
completed |
|
Building demolishen in Padanna |
In progress |
|
Demolition of 2 shops in P6 location |
In progress |
|
KSEB utility shifting near AP2 |
Completed |
|
BSNL cable shifting |
In progress |
|
P7b boring work |
completed |
SPT over, concreting started |
|
|
pile chipping at AP2 planned for next week |