   weekly progress 26.8.2011
    

 

Progress Report For Kainatty ROB for the week ending on 26-08-2011
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE KAINATTY  SIDE 18 18 0 0 0 0 0 0    
2 PILE NADAPURAM SIDE 27 27 0 0 0 0 0 0    
3 PILE CAP KAINATTY SIDE 6 4 2 2 2 0 2 2    
4 PILE CAP  NADAPURAM SIDE 9 7 2 2 2 0 2 2    
5 PIER KAINATTY  SIDE 6 4 2 2 3 0 2 2    
6 PIER NADAPURAM SIDE 9 8 1 1 1 0 1 1    
7 PIER CAP KAINATTY  SIDE 6 4 2 2 2 0 2 2    
8 PIER CAP NADAPURAM SIDE 9 6 3 1 2 1 1 1    
11 RE/R WALL KAINATTY  SIDE 100% 80% 20% 0 0.00% 0.00% 0.00% 0.00%    
10 RE/R WALL NADAPURAM SIDE 100% 80% 20% 0 0.00% 2.00% 0.00% 0.00%    
12 BEAM/SLAB  Staging Kainatty side 6 3 3 3 1 0 3 1    
13 BEAM/SLAB  Bar bending and Fixing Kainatty side 6 2.5 3.5 3 1 0.5 3.5 1    
14 BEAM/SLAB  Shuttering  and Concreting  Kainatty side 6 2 4 3 0 *0 4 1   *shuttering completed 50%
15 BEAM/SLAB  Staging Nadapuram side 9 3.1 5.9 3 0 0.9 5.9 0    
16 BEAM/SLAB  Bar bending and Fixing Nadapuram side 9 2.5 6.5 3 0 0.5 6.5 1    
17 BEAM/SLAB  Shuttering  and Concreting  Nadapuram side 9 2 7 3 0 2 5 0   *girder reinforcement for AP2-P13,P11-P12 complete
18 BEAM/SLAB KAINATTY  SIDE 6 0 6 0 0 1 0 0   P2-P3 girder concrete complete,shuttering work for slab P2-P3 in progress 
19 BEAM/SLAB NADAPURAM SIDE 9 0 9 0 0 0 0 0    
20 HR/FP/KERB KAINATTY  SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
21 HR/FP/KERB NADAPURAM SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
22 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
 
Back
 
    
VIEW FROM RAILWAY PIER

    
    
P10,P11-STAGING

    
    
P8-PIER CAP

    
    
P7-PIER CAP

    
 
    
P2,P3-GIRDER CONCRETE

    
    
AP2-P13-STEEL WORK

      
 

 

 

 

 

 

 

 