Prevoius Weekly Reports

   27.02.2010
    

ROB at Athani

Work Planned upto 27.02.2010 Completed/Progress Delay
RE wall works Medical College side Slow progress  
Fixing of panels 60m length 3 layer completed Delay due to shortage of earth for filling
Shornur side    
Friction slab Completed  
Friction slab kerb - Inner side Completed  
                          - Outer side in progress  
 
Back

No images are uploaded for this Weekly Reports

 
 
 

 

 

 

 

 

 

 