Prevoius Weekly Reports

   weekly progress 19.8.2011
    

 

Pile rig mobilisation at P13 a In progress  
Pile no 15 a boring completed Pile cage inserted
Site level survey completed  
7 day Cube test Completed  
BSNL, KWA site inspection for utility shifting In progress  
filling work in piling location In progress  
 
Back
 
    
TRIAL CUBES FOR PILING

    
    
P15A PILE REINFORCEMENT CAGE LOWERING

    
    
P15A PILE REINFORCEMENT CAGE LOWERING COMPLETE

    
    
P15A PILE BORING -DEPTH 26M

    
 
    
P15A PILE BORING - CHISSLE REPAIR

    
    
P15A PILE BORING - CHISSLE DAMAGE

      
 

 

 

 

 

 

 

 