RE wall works Medical College side RE wall works Medical College side ROB at Athani
Work Planned upto 06.03.2010 |
Completed/Progress |
Remarks |
RE wall works Medical College side |
No work |
|
Fixing of panels 60m length |
3 layer completed |
Delay due to shortage of earth for filling |
Shornur side |
|
|
Friction slab |
Completed |
|
Friction slab kerb - Inner side |
Completed |
|
- Outer side |
Completed |
|
|