   weekly progress 19.8.2011
    

 

Progress Report For Pulianam  ROB for the week ending on 19.08.2011 
Sl No   Activity Description   Total Quantity  Cumulative progress upto last week   Balance  work up to last week  Cumulative delay in Qty up to last week  Work  planned  during the week   Actual work done during the week   Cumulative delay in Qty up to this week  Work  Planned for next week  
1 Pile towards NH side 26 26 0 0 1 1 0 0
2 Pile towards Puliyanam side 18 6 12 1 2 0 2 4
3 Pile Cap Pulianam side 5 2 3 0 1 1 0 1
4 Pile Cap NH side 7 0 7 0 0 0 0 0

 

 

Date 13.08.2011 16.08.2011 17.08.2011 18.08.2011 19.08.2011
Climate Cloudy rainy pleasant rainy pleasant
No.of labours 40 42 42 39 42
availability of material    
materials Required Available
Fine aggregate(M3) 10 15
Coarse aggregate(M3) 20 30
Cement(BAG) 200 430
Steel(TONN) 6 28
 
Back
 
    
PILING WORK AT A2 LOCATION (17.08.2011).

    
    
PILING WORK AT P1 LOCATION (16.08.2011).

    
    
RC WALL 1ST LIFT SHUTTERING (18.08.2011).

    
    
PILE CHIPPING P3 LOCATION (16.08.2011)

    
 
    
P9 PILECAP CONCRETE (16.08.2011).

      
 

 

 

 

 

 

 

 