Prevoius Weekly Reports

   weekly progress 19.8.2011
    

 

Revised Progress Report For Ponnurunni ROB for the week ending on 18-08-2011
Si No  Activity Description  Total Quantity Cumulative progress upto 18.08.11 Balance  work up to 18.08.11 Cumulative delay in Qty up to18.08.11 Work  planned  during the week  Actual work done during the week  delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan
1 PILE  Palarivattom side(Approach portion) 31 28 3 0 0 0 0 0 kwa line to be shifted
2 PILE Palarivattom side(railway portion) 6 0 6 0 0 0 0 0 "      "
3 PILE vytilla side(Approach portion) 42 0 42 0 0 0 0 0 "      "
4 PILE vytilla side(railway portion) 6 0 6 0 0 0 0 0 kWA pipes and railway signal cable to be removed
5 PILE CAP Palarivattom side(Approach portion) 8 7 1 1 1 1 0 0 "      "
6 PILE CAP Palarivattomside(railway portion) 1 0 1 0 0 0 0 0 "      "
7 PILE CAP vytilla side(Approach portion) 9 0 9 0 0 0 0 0 "      "
8 PILE CAP vytilla side(railway portion) 1 0 1 0 0 0 0 0 "      "
9 PIER Palarivattom side(Approach portion) 8 7 1 0 3 1 0 0  
10 PIER Palarivattomside(railway portion) 1 0 1 0 0 0 0 0  
11 PIER Vytilla side(Approach portion) 9 0 9 0 0 0 0 0 "      "
12 PIER vytilla side(railway portion) 1 0 1 0 0 0 0 0 "      "
13 PIER  CAP Palarivattom side(Approach portion) 8 1 7 0 0 0 1 2  
14 PIER CAP Palarivattomside(railway portion) 1 0 1 0 0 0 0 0  
15 PIER CAP  Vytilla side(Approach portion) 9 0 9 0 0 0 0 0 "      "
16 PIER CAP vytilla side(railway portion) 1 0 1 0 0 0 0 0 "      "
17 RE WALL PANEL 370 344 26 2 12 10 4 12 0

 

Labour Report              
               
Date 12.08.11 13.08.11 14.08.11 15.0811 16.08.11 17.08.11 18.08.11
Day Fri Sat Sun Mon Tue Wed Thurs
Climate rainy sunny sunny sunny sunny Sunny Sunny
No.of labours 21 22 12 1 18 23 23
               
               
Availability of Material               
               
Materials Required for week ending on 18.08.11 Available as on 12.08.2011          
Fine aggregate(M3) Ready Mix Concrete          
Coarse aggregate(M3)          
Cement(BAG)          
Steel(TONN) 1.6 28.2          
 
Back
 
    
SLUMP TEST(17.8.2011)

    
    
RE WALL PANEL REINFORECEMENT(16.8.2011).

    
    
PIER CAP P15 REINFORCEMENT(17.8.2011).

    
    
DE SHUTTERING PIER P10(12.8.2011).

    
 
    
CONCRETING PIER CAP P15(17.8.2011)F

    
    
CONCRETING PIER CAP P15(17.8.2011)

      
 

 

 

 

 

 

 

 